Compelling Ore Sorting Work at Reward
Released
Released
Announcement PDF
Reward Gold Mine Ore Sorting Results Compelling,
79% Mass Reduction & 337.20% increase in Grade.
ASX Announcement 25th July 2024
•
Ore sorting/pre-concentration testwork completed at TOMRA facility.
•
TOMRA’s LASER sorting technology (Sorter) separates gold bearing quartz ore from waste (slate &
greywacke) before it enters the processing plant.
94kg of sample from the low-grade stockpile at Reward Gold Mine (Reward) was sorted. The
following results are reported;
✓ Head grade to Sorter weighted average grade (WAG) = 3.70 g/t gold,
✓ Ore grade WAG after sorting = 16.22g/t gold (337.20% increase on grade),
✓ Ore/waste split after sorting = 19.31kgs Ore vs 74.54kgs Waste (79% mass reduction),
✓ Gold lost to waste fraction = 0.03grams (>90% efficiency)
•
•
The above figures underpin the usefulness of the TOMRA LASER sorter in sorting material from
Reward.
Vertex believe ore sorting technology can positively impact the sustainability and profitability of
Vertex’s operations at Reward by;
•
Processing high-grade ore post sorting, resulting in reduced;
✓ energy & water consumption, leading to,
✓ lower operating costs and
✓ reduced carbon footprint.
•
Tailings material volume can be significantly reduced in volume, leading to further ESG benefits and
cost savings.
Ore sorting also provides the opportunity to process stockpiles economically while we develop
underground
•
Work is being undertaken regarding the inclusion of a TOMRA LASER sorter into the plant currently
being refurbished/modified by Gekko. More to follow.
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
Vertex Minerals Limited (ASX:VTX) (“Vertex” or the “Company”) is pleased to report the ore sorting
results for the Reward Gold Mine in Hill End NSW. The Company completed an ore sorting program with
TOMRA to assess the potential of upgrading the ore prior to further processing through the Hill End
Gravity Gold Mill. A total of 160kg of material was transported to the TOMRA ore sorting facilities in
Sydney. A Test was conducted using laser sorting technology.
Commenting on the results, Executive Chairman, Roger Jackson, said “The ore sorting results are
compelling and confirm the Reward Gold ore is perfectly suited for this technology. By upgrading the
Reward high-grade ore material to an even higher grade significantly enhances the potential of Reward
by reducing processing costs and increasing the returns per tonne”.
Sorting Test Work
Material sorting test-work was completed to determine the suitability of the Reward Gold Mine
mineralised material to be upgraded using advanced ore sorting technology provided by TOMRA
Sorting Australia. These results are considered to be “proof-of-concept” tests by TOMRA and were
conducted on a representative sample of mineralised material collected from the low grade
stockpiles (development material) derived from the Reward Gold Mine.
A total of 156kg of mineralised material was collected, by Vertex geologist, from said stockpiles
(stockpile sample), with a weighted average grade of 3.73g/t Au. For the purposes of the test-work,
the sample was screened to 19mm-48mm and separated into a <19mm/undersize fraction (62.51kg
@ 3.77g/t Au) which was not sorted (ie too fine) and a TOMRA Feed stream. The TOMRA Feed was
then sorted, using the TOMRA LASER sorter into ore (quartz with gold) and waste (slate &
greywacke) streams. The upgrade factor, which includes the ore stream, together with the undersize
material, resulted in a gold upgrade of 79.89%, a decrease in sample mass of 48%, and only ~5% loss
in contained gold.
Results generated from this set of testwork were successful. An excellent gold upgrade was achieved
for this sample using TOMRA’s LASER system targeting and ejecting vein quartz away from lowgrade host-rock. Figure 1 shows performance of TOMRA’s PRO LASER sorter for the 20-60mm
sample.
Figure 1 Grade v sorting graph
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
Table 1 Au grades comparison of sorted ore
Mass
Au
Size
Fraction
20-60mm
-20mm
Fraction
ppm
kg
%
Feed
3.71
94
100%
Product
16.2
19.4
21%
Waste
0.46
74.6
79%
Fines
3.77
N/A
N/A
Table 1 shows the sorted masses and gold grades for all sorted fractions as well as back-calculated
feed grades produced by this set of testwork. The primary sorting task was to investigate the
sortability of material from the Reward deposit as well as the reliability of the gold / quartz
association. As TOMRA’s LASER system detects, classifies, and ejects quartz, this association is
paramount to the amenability of this ore to ore-sorting using LASER.
Results of the testwork are considered very successful. A single-stage sort was able to produce a
16.2ppm Au product grade and 0.46ppm Au waste grade from a 3.71ppm Au feed grade with a 79%
mass reduction.
Success can be attributed to several factors:
•
•
•
The ability of TOMRA’s LASER system to detect, classify, and eject quartz away from the relatively
low-grade host-rock
The liberation of quartz from host-rock at this size fraction
The reliability of gold association to quartz in this ore
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
Figure 2 Photo of accepted Gold bearing quartz on left and barren sorted greywacke on right
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
Figure 3 Tomra Laser Sorter
Figure 4 Sorter schematic
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
Table 2 Summary of sorting results of the low-grade gold from Reward using laser including the unsorted under
20mm material
Stockpile Material
Rejected Waste
Weight
kg
156.36
74.45
under 19mm
Accepted Ore
62
19.31
Total
Washed fines
155.76
0.6
Mass % to process
Grams to plant
Grade to plant
Grade upgrade
81.31
Grade
Total grams Percentage
g/t
g
%
3.72
583.2
0.06
4.5
0.77%
3.7
16.22
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
229.4
313.2
39.33%
52%
52%
542.6
6.67
80%
MINERAL RESOURCE
•
Combined Mineral Resource Estimate (MRE) for the Reward gold deposit at Hill End stands at 419,000
tonnes at 16.72g/t Au for 225,200oz Au (VTX Announcement 21 June 2023)
Table 3 – Reward Resource Estimate
Classification
Cut-off
Tonnes
Au (g/t)
Ounces
Indicated
4
141,000
15.54
70,500
Inferred
4
278,000
17.28
154,700
Total
4
419,000
16.72
225,200
HILL END GLOBAL RESOURCE
Table 4: Global Mineral Resource estimate for the Hill End & Hargraves Gold Project
Hill End Project Mineral Resource Estimate
Deposit
Classification
Tonnes
(kt)
Grade
Au (g/t)
Contained
Au (koz)
141
278
15.5
17.3
71
155
419
16.7
225
1,109
1,210
2.7
2.1
97
80
2,319
2.4
178
413
1,063
1.4
1.8
19
61
1,476
1.7
80
1,663
2,551
4,214
3.5
3.6
3.6
187
296
483
Reward Gold Mine
Indicated
Inferred
Sub Total
Hargraves Project
Indicated
Inferred
Sub Total
Red Hill Project
Indicated
Inferred
Sub Total
Project Total
Indicated
Inferred
Grand Total
FOSTERS EXPLORATION TARGET
Table 5: Exploration Target for Fosters (adjacent to Reward Gold Mine)
Deposit
Range
Tonnes (kt)
Au (g/t)
Ounces Au (koz)
Fosters
Lower
Range
Upper
Range
524
12.5
211
524
19
320
VTX Announcement High Grade Exploration Target Estimate at hill End 29th of August 2023
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
Cautionary Statement
The Exploration Target is conceptual in nature as there has been insufficient exploration to define a
Mineral Resource. It is uncertain if further exploration will result in the determination of a Mineral
Resource under the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves, the JORC Code” (JORC 2012). The Exploration Target is not being reported as part of any
Mineral Resource or Ore Reserve.
Competent Persons Statements
The information in this report that relates to Exploration Results and Exploration Targets is based on
information compiled by Mr. Roger Jackson, a Director and Shareholder of the Company, who is a
25+ year Fellow of the Australasian Institute of Mining and Metallurgy (FAusIMM), Fellow of the
Australian Institute of Geoscientists (FAIG) and a Member of Australian Institute of Company
Directors. Mr. Jackson has sufficient experience which is relevant to the style of mineralisation and
type of deposits under consideration and to the activity which he is undertaking to qualify as a
Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of
Exploration results, Mineral Resources and Ore Reserves”. Mr. Jackson consents to the inclusion of
the data contained in relevant resource reports used for this announcement as well as the matters,
form and context in which the relevant data appears.
Forward Looking Statements and Important Notice
This report contains forecasts, projections, and forward-looking information. Although the Company
believes that its expectations, estimates and forecast outcomes are based on reasonable assumptions
it can give no assurance that these will be achieved. Expectations and estimates and projections and
information provided by the Company are not a guarantee of future performance and involve
unknown risks and uncertainties, many of which are out of Vertex Minerals’ control.
Actual results and developments will almost certainly differ materially from those expressed or
implied. Vertex Minerals has not audited or investigated the accuracy or completeness of the
information, statements and opinions contained in this announcement. To the maximum extent
permitted by applicable laws, Vertex Minerals makes no representation and can give no assurance,
guarantee or warranty, express or implied, as to, and takes no responsibility and assumes no liability
for the authenticity, validity, accuracy, suitability or completeness of, or any errors in or omission
from, any information, statement or opinion contained in this report and without prejudice, to the
generality of the foregoing, the achievement or accuracy of any forecasts, projections or other
forward looking information contained or referred to in this report.
Investors should make and rely upon their own enquiries before deciding to acquire or deal in the
Company’s securities.
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
This announcement has been approved by the Board of Vertex Minerals Limited.
Further Information:
Roger
Jackson
Executive Chairman
roger@vertexminerals.com.au
Tully
Richards
Director
Technical
tully@vertexminerals.com.au
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
About Vertex Minerals Limited
STRATEGIC FOCUS
•
Clear Strategy set for Hill End
1. To install a circa 110ktpa Gravity Gold plant in 2024
2. To commence gold production from existing stockpiles
3. Commence mining development in the high-grade Reward Mine in late 2024
4. To commence at a reduced throughput, but with ore sorting, with a build up of
throughput through 2025
5. To be Australia’s most prominent high grade gold miner
6. To drill and add high grade gold to the global Hill End gold inventory, from the largescale gold system/s within the Hill End Corridor.
7. To take the existing resources and near surface mineralisation to production utilising
gravity gold recovery methods.
8. Earn a robust Safety , Environmental, Social and Governance (ESG) reputation.
9. Build shareholder value
Vertex Minerals Limited (ASX: VTX) is an Australian based gold exploration company developing
its advanced Hargraves and Hill End gold projects located in the highly prospective Eastern Lachlan
Fold Belt of Central West NSW. Other Company assets include the Pride of Elvire gold project and
Taylors Rock gold/nickel/lithium project both located in the Eastern Goldfields of WA. The focus
of Vertex Minerals is to advance the commercial production of gold from its NSW projects
embracing an ethical and environmentally sustainable approach:
✓ Gravity Recoverable Gold
✓ Low Capex and Low Operating cost
✓ Minimal grind 200 to 500 micron
✓ Benign tails – potential commercial sand
✓ Benign waste
✓ Low water usage
✓ Re usable water
✓ No chemicals – no cyanide
✓ 23 fine gold
✓ Minimum tails to productivity
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
Hargraves Gold Project (NSW)
•
•
•
Hargraves Gold project is located approximately 2 5 km south of the town of Mudgee.
The goldfield is 4 x 10 km with numerous mineralised structures with little modern
exploration.
An updated mineral resource in accordance with JORC 2012 Code was completed by SRK
Consulting (Australasia) Pty Ltd (SRK) – total of 2.3Mt at 2.38g/t Au for 177koz Au.
Hill End Gold Project (NSW)
•
•
Consists of 10 mining leases and three Exploration Licences located in the core of the Hill End
Trough on the eastern Lachlan Fold Belt.
14km of continuous gold lode with gold recovery rate to gravity at +90%.
Pride of Elvire Gold Project (WA)
•
•
Tenements surround the Mt. Elvire homestead approximately 210km north of Southern
Cross in Western Australia
The project has seen historical drilling with encouraging gold results achieved.
Taylors Rock Project (WA)
•
•
Located 80km WSW of Norseman in the Southern Goldfields region of Western Australia.
The project has both Gold Lithium and Nickel potential, interesting historical intercepts have
recorded encouraging mineralisation.
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
APPENDIX 1 - JORC CODE, 2012 EDITION – TABLE 1 – REWARD GOLD MINE ORE SORTING
Section 1 Sampling Techniques and Data
Criteria
Sampling techniques
JORC Code explanation
Commentary
•
•
•
•
•
Drilling techniques
Drill sample recovery
•
•
•
•
Logging
•
•
Sub-sampling
techniques and
sample preparation
•
•
•
•
•
•
Quality of assay data
and laboratory tests
•
•
•
•
Nature and quality of sampling (eg cut channels, random chips, or specific specialised
industry standard measurement tools appropriate to the minerals under investigation, such
as down hole gamma sondes, or handheld XRF instruments, etc). These examples should not
be taken as limiting the broad meaning of sampling.
Include reference to measures taken to ensure sample representivity and the appropriate
calibration of any measurement tools or systems used.
Aspects of the determination of mineralisation that are Material to the Public Report.
In cases where ‘industry standard’ work has been done this would be relatively simple (eg
‘reverse circulation drilling was used to obtain 1 m samples from which 3 kg was pulverised
to produce a 30 g charge for fire assay’). In other cases more explanation may be required,
such as where there is coarse gold that has inherent sampling problems.
Drill type (eg core, reverse circulation, open-hole hammer, rotary air blast, auger, Bangka,
sonic, etc) and details (eg core diameter, triple or standard tube, depth of diamond tails,
face-sampling bit or other type, whether core is oriented and if so, by what method, etc).
Method of recording and assessing core and chip sample recoveries and results assessed.
Measures taken to maximise sample recovery and ensure representative nature of the
samples.
Whether a relationship exists between sample recovery and grade and whether sample bias
may have occurred due to preferential loss/gain of fine/coarse material.
Whether core and chip samples have been geologically and geotechnically logged to a level
of detail to support appropriate Mineral Resource estimation, mining studies and
metallurgical studies.
Whether logging is qualitative or quantitative in nature. Core (or costean, channel, etc)
photography.
The total length and percentage of the relevant intersections logged.
If core, whether cut or sawn and whether quarter, half or all core taken.
If non-core, whether riffled, tube sampled, rotary split, etc and whether sampled wet or dry.
For all sample types, the nature, quality and appropriateness of the sample preparation
technique.
Quality control procedures adopted for all sub-sampling stages to maximise representivity of
samples.
Measures taken to ensure that the sampling is representative of the in situ material collected,
including for instance results for field duplicate/second-half sampling.
Whether sample sizes are appropriate to the grain size of the material being sampled.
The nature, quality and appropriateness of the assaying and laboratory procedures used and
whether the technique is considered partial or total.
For geophysical tools, spectrometers, handheld XRF instruments, etc, the parameters used in
determining the analysis including instrument make and model, reading times, calibrations
factors applied and their derivation, etc.
Nature of quality control procedures adopted (eg standards, blanks, duplicates, external
•
Samples were selected for from the Reward Gold Mine Waste piles, as representative of the Ore
using a hand-held scoop.
The geology of the reward Gold Mine is auriferous subvertical quartz veins with greywacke
or turbidite country rock.
•
N/A. Samples were from mining.
•
N/A. Samples were from mining.
•
N/A. Samples were from mining. Geological logging was not relevant to the processing test
work.
•
•
Samples were from mining. Scooped samples were placed in 20 litre plastic buckets.
QAQC is limited to the internal lab procedures. Duplicates were not collected for this sampling
programme.
The samples are believed to be representative for the purposes for which they were collected.
•
Samples were assayed at ALS Orange using Fire Assay with a 50g charge.
Criteria
Verification of sampling
and assaying
Location of data points
JORC Code explanation
•
•
N/A. Samples were from mining.
•
Sample locations were taken from the operational mining stockpiles
Data spacing for reporting of Exploration Results.
Whether the data spacing and distribution is sufficient to establish the degree of geological
and grade continuity appropriate for the Mineral Resource and Ore Reserve estimation
procedure(s) and classifications applied.
Whether sample compositing has been applied.
Whether the orientation of sampling achieves unbiased sampling of possible structures and
the extent to which this is known, considering the deposit type.
If the relationship between the drilling orientation and the orientation of key mineralised
structures is considered to have introduced a sampling bias, this should be assessed and
reported if material.
•
N/A. Samples were from mining.
•
N/A. Samples were from mining. They are from blasted material
•
There is no known sample biasing.
•
The measures taken to ensure sample security.
•
The samples were transported to ALS Orange via our Director
•
The results of any audits or reviews of sampling techniques and data.
•
No audit was undertaken for this programme.
•
•
•
•
•
Data spacing and
•
•
distribution
•
•
Orientation of data in
relation to geological
•
structure
Sample security
Audits or reviews
laboratory checks) and whether acceptable levels of accuracy (ie lack of bias) and precision
have been established.
The verification of significant intersections by either independent or alternative company
personnel.
The use of twinned holes.
Documentation of primary data, data entry procedures, data verification, data storage
(physical and electronic) protocols.
Accuracy and quality of surveys used to locate drill holes (collar and down-hole surveys),
trenches, mine workings and other locations used in Mineral Resource estimation.
Specification of the grid system used.
Quality and adequacy of topographic control.
Commentary
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria
Mineral tenement and
land tenure status
JORC Code explanation
Commentary
•
•
•
•
Exploration done by
other parties
Type, reference name/number, location and ownership including agreements or material
issues with third parties such as joint ventures, partnerships, overriding royalties, native title
interests, historical sites, wilderness or national park and environmental settings.
The security of the tenure held at the time of reporting along with any known impediments
to obtaining a licence to operate in the area.
Acknowledgment and appraisal of exploration by other parties.
•
•
•
•
•
The project is located within granted Exploration Licence EL5868 Mining leases
ML1541, ML1116, ML315, ML316, ML317, ML49,
ML50, ML913, ML914, ML915 and GL5846 with the earliest expiry date of 19 January
2033. The leases are held by Vertex Minerals Pty Ltd.
First Tiffany Resources Corporation is registered as having a 15% free carried
interest in EL5868.
The site is covered by EPL 12008, scheduled activity is mining for minerals.
The tenure is 100% owned by Vertex
The historical exploration data has been collected by Vertex Limited and has been reported
to high standards.
The methods of exploration and techniques used are considered appropriate for the deposit
types sought (Au)
Criteria
Geology
Drill hole Information
Data aggregation
methods
Relationship
JORC Code explanation
Commentary
•
Deposit type, geological setting and style of mineralisation.
•
Reef gold
•
A summary of all information material to the understanding of the exploration results
including a tabulation of the following information for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above sea level in metres) of the drill hole
collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
•
N/A as they were collected at stockpiles
•
In reporting Exploration Results, weighting averaging techniques, maximum and/or
minimum grade truncations (eg cutting of high grades) and cut-off grades are usually
Material and should be stated.
Where aggregate intercepts incorporate short lengths of high grade results and longer
lengths of low grade results, the procedure used for such aggregation should be stated and
some typical examples of such aggregations should be shown in detail.
The assumptions used for any reporting of metal equivalent values should be clearly stated.
If the geometry of the mineralisation with respect to the drill hole angle is known, its nature
should be reported.
If it is not known and only the down hole lengths are reported, there should be a clear
statement to this effect (eg ‘down hole length, true width not known’).
•
N/A No aggregation methods were used oor required for this test work
•
N/A Stockpile material
Appropriate maps and sections (with scales) and tabulations of intercepts should be
included for any significant discovery being reported These should include, but not be
limited to a plan view of drill hole collar locations and appropriate sectional views.
Where comprehensive reporting of all Exploration Results is not practicable, representative
reporting of both low and high grades and/or widths should be practiced to avoid
misleading reporting of Exploration Results.
Other exploration data, if meaningful and material, should be reported including (but not
limited to): geological observations; geophysical survey results; geochemical survey results;
bulk samples – size and method of treatment; metallurgical test results; bulk density,
groundwater, geotechnical and rock characteristics; potential deleterious or contaminating
substances.
The nature and scale of planned further work (eg tests for lateral extensions or depth
extensions or large-scale step-out drilling).
Diagrams clearly highlighting the areas of possible extensions, including the main geological
interpretations and future drilling areas, provided this information is not commercially
sensitive.
•
N/A. Samples were from existing mining areas. Next to the Hill End Gravity Gold Plant
•
All relevant assays have been reported.
•
All relevant geological information has been reported.
•
N/A. Samples were from existing mining areas.
•
between
mineralisation widths
•
•
•
and intercept lengths
Diagrams
Balanced reporting
Other substantive
•
•
•
exploration data
Further work
•
•
Share your feedback
Discover