ASX ANNOUNCEMENT
31 January 2024
ABN 68 650 116 153
QUARTERLY ACTIVITIES REPORT
FOR THE PERIOD ENDED 31 DECEMBER 2023
HIGHLIGHTS FOR QUARTER
§ First Gold poured after trial-processing the Hill End Plant Stockpiles. (on limited
plant throughput)1.
§ Significant step forward to gold production with commencement of the Reward
High Grade gold mine Pre-Feasibility Study.2
§ Engagement of Ground Control Engineering and Gekko Systems to undertake
Mining and processing components of the PFS.
§ Extensive refurbishments completed to expand plant capacity and prepare for
future underground mine operations.
ü Refurbishment of the Change rooms
ü Refurbishment of the Crib room
ü Water recycling systems
ü Satellite communication installation
ü Security system installation
ü Safety system implementation
ü HR planning
ü Jaw Crusher refurbishment
ü Underground truck refurbishment
ü Surface loader refurbishment
§ Acquisition of
ü 25-ton Caterpillar excavator
ü 6m Wilfley table for the gold room
ü Polaris 4wd
Page 1 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
§ Further high-grade gold targets identified south of Vertex’s Hill End Gold Plant and
Reward Resource by ground-truthing LiDAR data around the South Star group of
mines (refer to Figure 1).3
§ Multiple parallel gold-bearing quartz veins at South Star strike >800m. (Figure1)
•
South Star lies 1.5km south of the Hill End Gold Plant and has the
potential to provide future feed along with the Fosters Exploration
target.
§ An Exploration Target has been calculated for Fosters Gold Project (Fosters),
around 400m south of the Reward Gold Mine (refer to Figure 1). Independent
geologists HGS Australia calculated the following Exploration Target: 4
•
524kt @ 12.5g/t Au (lower range) 211kozs
•
524kt @ 19.0g/t Au (upper range) 321kozs
•
The Fosters Exploration Target is within ground covered by the
Company’s Mining Licences (ML’s) and existing Development
Consent
•
Fosters is accessed by an existing adit and development drive;
Fosters adit is a few hundred meters from the Hill End Gravity Gold
plant.
•
Additionally, Fosters is open at depth and along strike to the North
and the South (refer to Figure 1)
Cautionary Statement
The Exploration Target is conceptual in nature as there has been insufficient exploration to
define a Mineral Resource. It is uncertain if further exploration will result in the
determination of a Mineral Resource under the “Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves, the JORC Code” (JORC 2012). The
Exploration Target is not being reported as part of any Mineral Resource or Ore Reserve
§ The Exploration Target complements the Mineral Resource Estimate (MRE) for the
Reward gold deposit at Hill End that now stands at 419,000 tonnes at 16.72g/t Au
for 225,200oz Au 5 (which forms the base case PFS feed to the Hill End Gravity gold
plant) ;
Classification
Indicated
Inferred
Total
Cut-off
4
4
4
Tonnes
141,000
278,000
419,000
Au (g/t)
15.54
17.28
16.72
Ounces
70,500
154,700
225,200
1
Stockpile results referred to in ASX Announcement 27th of April 2023
VTX ASX announcement 3rd of January 2024
3
VTX ASX announcement 4th of December 2023
4
VTX ASX announcement 29th of August 2023
2
Page 2 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
5
VTX ASX announcement 5th of July 2023
Figure 1 Showing Reward Resource, Fosters Exploration target and the South Star lodes. All of
which can potentially provide feed to the Hill End Gravity plant.
Page 3 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
STRATEGIC FOCUS
Clear Strategy set for Hill End:
1. To increase the capacity of the Gravity Gold plant in the first half of 2024.
2. To commence gold production from existing stockpiles.
3. Initiate underground mining development in the high-grade Reward Mine in
2024.
4. To be amongst Australia’s highest grade gold miners.
5. To drill and add high grade gold to the global Hill End gold inventory from the
large-scale gold system/s within the Hill End Corridor.
6. To achieve gold production within 12 months from the existing resource and
exploration targets on granted Mining Licences utilising gravity gold recovery
methods.
7. Earn a robust Safety, Environmental, Social and Governance (ESG) reputation.
8. Build shareholder value.
Figure 2 Hill End Underground Mine Infrastructure
Page 4 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
Figure 3 Location of the 100% owned Hill End Gold Mine
Page 5 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
EVENTS SUBSEQUENT TO QUARTER END
REWARD HIGH GRADE GOLD MINE PFS
Cautionary Statement
The production target and forecast financial information referred to in this announcement
comprise Indicated Mineral Resources (~75%) and Inferred Mineral Resources (~25%). There
is a lower level of geological confidence associated with the Inferred Mineral Resource and
there is no certainty that further exploration work will result in an upgrade to an Indicated
Mineral Resource or that the production target will be achieved.
The study documented in this announcement is considered to have a +/-25% PFS level of
accuracy.
The Pre- Feasibility Study referred to in this announcement is based on a JORC Mineral
resources Estimate (Refer ASX Release: Vertex Reward Gold Resource Upgrade estimate 21
June 2023) the Ore Reserves and Mineral resource estimate underpinning the PFS have been
prepared by Competent Persons in accordance with the 2012 JORC Code.
The Company advises that the Probable Ore Reserve provides 76% of the total milled tonnage
and 75% of the total contained gold metal. The production target referred to is based on
Mineral Resource estimates which are classified as Indicated (76.6%) and Inferred (23.4%)
The Pre-Feasibility Study is based on the material assumptions outlined below. These include
assumptions about the availability of funding. While Vertex considers all of the material
assumptions to be based on reasonable grounds, there is no certainty that they will prove to
be correct or that the range of outcomes indicated by the Pre-Feasibility Study will be
achieved. To achieve the range of outcomes indicated in the Pre-feasibility Study, funding in
the order of $28 million will likely be required. Investors should note that there is no certainty
that Vertex will be able to raise that amount of funding when needed. It is also possible that
such funding may only be available on terms that may be dilutive to or otherwise affect the
value of Vertex’s existing shares. Given the uncertainties involved, investors should not make
any investment decisions based solely on the results of the Pre-Feasibility Study.
PFS HIGHLIGHTS:
Project Life
2 years
of minerals processing activities
Gold Production
49,890 ounces
Gross Revenue
$150 million
Capital Expenditure
$28.5 million
Pre-production
AISC
$1,712 per ounce
Total Employment
70
Full time employees
Free Cashflow
$35.7 million
pre tax
NPV at 7%
$28.3 million
pre tax
IRR
77%
pre tax
Page 6 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
All dollars are Australian Dollars ($) unless stated otherwise.
Key Parameters
•
Life of mine pre-tax cash of $35.7 million at $3,000/oz gold price.
•
9-month payback
•
Average monthly gold production of 2,169 oz over 23 months with 92% gold recovery.
•
Mine design based on mechanised mining methods. Long hole open stoping with
remotely operated loaders was selected as the primary stoping method.
•
Planned processing of 181kt of material at a head grade of 9.3 g/t for 49,890 ounces of
gold recovered.
Maiden Ore Reserve
•
Probable Ore Reserve of 130kt at 9.7 g/t Au, containing 40,900 ounces of gold.
•
Reserve represents 75% of LOM metal production.
Mineral Resource & Exploration
•
Production schedules and financial estimates are based on Indicated Mineral
Resources (~75% of Au) and Inferred Mineral Resources (~25% of Au).
•
Combined Mineral Resource Estimate (MRE) for the Reward gold deposit at Hill End
stands at 419,000 tonnes at 16.72g/t Au for 225,200oz Au (VTX Announcement 21 June
2023)
Table 1 – Reward Resource Estimate
Classification
Indicated
Inferred
Total
Cut-off
4
4
4
Tonnes
141,000
278,000
419,000
Au (g/t)
15.54
17.28
16.72
Ounces
70,500
154,700
225,200
•
The best platforms for further exploration drilling are from the underground mine due
to the rugged terrain of the area (see Figure 2). The proposed development provides
access to explore down dip and along strike.
•
Mine development provides the best opportunity to efficiently diamond drill, add to
the resource base (size and confidence category) and potentially extend life of mine.
Mineral Processing
•
Gold recovery of 92% achieved using gravity separation techniques. No requirement
for the use of cyanide or other chemicals.
•
Planned plant upgrade to 120ktpa throughput.
•
Capital expenditure on processing plant of $7.3 million.
Page 7 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
The Reward gold mine is well –placed for a simple start –up:
•
The existing gravity processing plant is located adjacent to the underground mine portal
(640 Level) and the Company plans to increase throughput to 120ktpa.
•
•
The 640 Level extends into the resource and stripping and refurbishment of this
development is required.
Second egress in place with ladder way and motorised Alimak shaft conveyance.
•
Some underground fleet and utility services are already in place.
•
Mining Licence and DA in place for processing plant, stockpiles and the underground
mine.
•
Permitted residue storage has capacity for the commencement of operations.
The Board of Directors recognise that the conversion of the Inferred Resource to an Indicated
Resource through more drilling would significantly enhance the Projects key financial metrics. The
decision to undertake a PFS on the current resource base reflects the significantly improved
exploration drilling outcomes that will be achieved through drilling from new development within the
underground mine. The Project topography limits drill platforms, and the existing underground
workings are all within the mineralised corridor. The workings do not provide sufficient access to the
hanging wall to provide good exploration drill locations.
The positive financial outcome from the PFS provides a justification for the development of a mine
plan that will significantly enhance the ability for the Company to upgrade the Inferred Mineral
Resource by way of improved access. Importantly, this also allows more effective exploration of the
mineralised corridor below and on strike of the existing mineral resource. Whilst exploration success
is not guaranteed, it is the Board’s opinion that this strategy provides the most effective way to
increase mine life.
Whilst alternative development options were considered, the pathway outlined in the PFS provided a
significantly more robust financial outcome and maximised the extraction of the Indicated Mineral
Resource. Whilst the PFS included some Inferred Mineral Resource in the mine plan and financial
models, this material was coincidental to the stope and development designs. The mine design
targeted the Indicated Mineral Resource.
It is the Board’s opinion that development of the mine in parallel with underground exploration drilling
will provide the best opportunity to improve the Project’s financial outcome.
ENVIRONMENTAL AND SUSTAINABLE MINING
•
•
•
•
•
•
•
•
•
•
Gravity Recoverable Gold
Low Capex and Low Operating cost
Minimal grind 200 to 500 micron
Potential renewable energy – Wind – pump storage
Benign tails – potential commercial sand
Benign waste
Low water usage
Re usable water
No chemicals – no cyanide
23 fine gold
Page 8 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
CORPORATE & FINANCIAL
As at 31 December, 2023, the Company held A$551,223 in cash.
Vertex’s expenditure during the Quarter was as follows:
Item
A$ (‘000s)
Cash Balance at beginning of Quarter
1,236
Sale of gold
53
Administration and Corporate Costs
(166)
Exploration and Evaluation
(247)
Acquisition of property, plant and equipment
(306)
Repayment of borrowings
(19)
Cash Balance at End of Quarter
551
During the quarter, the Company made payments of $137,000 to related parties in relation
to Directors’ fees and consulting fees for both technical and management services.
Page 9 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
Appendix 1 – Additional ASX Information
Listing Rule 5.3.4 Use of funds
VTX was admitted to trading on the ASX on 12 January 2022. The 31 December 2023 quarter
is included in a period covered by a Use of Funds statement in a prospectus lodged with ASX
under Listing Rule 1.a, condition 3. A comparison of the Company’s expenditure against the
estimated Use of Funds statement is set out below as required under Listing Rule 5.3.4.
Expenditure item
Exploration at the
projects
Cash reimbursement to
project vendors
Expenses of the offer
Administration costs
Department of Regional
NSW – bonds transfer
Working capital
Note
1
2
1
3
Use of
Funds
(2 years)
$
Actual to 31
December 2023
(excluding GST)
$
Variance
$
2,420,000
2,870,788
450,788
617,759
650,000
1,060,000
617,759
795,065
1,583,632
145,065
523,632
185,000
887,241
5,820,000
185,000
173,369
6,225,613
(713,872)
(2,053)
Note:
1. The Use of Funds statement covers a 2 year period whereas current actual
expenditure covers the period since incorporation. Expenditure items are budgeted
to be incurred over the full 2 year period with expenditure on exploration at the
projects only occurring post listing.
2. Legal fees, shareholder engagement and administration fees were higher than
anticipated in the offer.
3. VTX has concentrated exploration activities to date at the projects included in the
prospectus.
Page 10 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
TENEMENT INFORMATION (LISTING RULE 5.3.3)
Tenements acquired or disposed during the Quarter
N/A
Mining tenements held at the end of the Quarter
Tenement
Project
Status
Area
LOCATION
EL 5868
EL 6996
EL 8289
EL 9247
EL 9413
GL 5846
Hill End
Hargraves
Hill End
Hill End
Hill End
Hill End
Renewal Pending
Renewal Pending
Current
Current
Current
Current
16 Units
6 Units
1 Unit
2 Units
1 Unit
2.044 ha
NSW
NSW
NSW
NSW
NSW
NSW
ML 49
ML 50
ML 315
ML 316
ML 317
ML 913
ML 914
ML 915
ML 1116
ML 1541
ELA 6466
EPL 12008
E77/2651
E 63/2058
ELA 6466
EPL 12008
Hill End
Hill End
Hill End
Hill End
Hill End
Hill End
Hill End
Hill End
Hill End
Hill End
Hill End South
Hill End
Pride of Elvire
Taylors Rock
Hill End South
Hill End
Current
Current
Current
Current
Current
Renewal Pending
Renewal Pending
Renewal Pending
Current
Current
Application Pending
Issued
Current
Current
Application Pending
Issued
1.618 ha
3.02 ha
6.671 ha
8.846 ha
7 ha
22 ha
21.69 ha
13.27 ha
15.71 ha
279.2 ha
30 Units
51km2
57km2
30 Units
-
NSW
NSW
NSW
NSW
NSW
NSW
NSW
NSW
NSW
NSW
NSW
WA
WA
-
Interests may be held directly by the Company, a subsidiary, or contractually.
Farm-in or Farm-out Agreements entered into during the Quarter
N/A
Beneficial Percentage Interests Held in Farm-in or Farm-out agreements at the end of the
Quarter
N/A
Page 11 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
Page 12 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
ABOUT VERTEX
Hill End NSW:
• 14km of Continuous gold lode
• Gold recovers to gravity at +90%
• Most of the line of lode only mined to the water table
• The Hill End Gold project consists of 10 mining leases & 4 Exploration licenses located
in the core of the Hill End Trough on the eastern Lachlan Fold Belt.
• The area was first recognised as a gold centre in 1851 with a number of mining
operations established over the following 50 years
• Modern exploration has not been completed and a program of multi-element and
alteration mapping has been planned to better map out the zones of high-grade
mineralisation.
• Recent completion of a full geological review of the Hill End Gold Project and an
updated geological model - expected to underpin a new exploration campaign.
• Largest Gold Specimen ever to be found globally found at Hill End
• Gravity Plant on site
• Fully permitted Gravity processing licence
Page 13 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
Reward Gold Mine: 2.0g/t reporting cutoff grade
Hargraves: 0.8 g/t reporting cutoff grade (ASX Announcement 29 May 2020).
Red Hill: 0.5 g/t per block, ordinary kriging grade interpolation, classified mineral Resources Limited to 160mRL below surface.
(ASX Announcement November 2015)
Hargraves NSW:
• Hargraves Gold project is located approximately 25km south of the town of Mudgee.
• The goldfield is 4 x 10 km with numerous mineralised structures with little modern
exploration.
• An updated mineral resource in accordance with JORC 2012 Code was completed by
SRK Consulting (Australasia) Pty Ltd (SRK).
• The Board will prioritise the development of this project by updating PFS, permitting
and further drilling to increase resources.
Taylor Rock WA:
• The Taylor Rock Project is located 80km WSW of Norseman in the Southern Goldfields
region of Western Australia
• The project has both Gold and Nickel potential, interesting historical intercepts
include:
§ 12NLJC0005: 2m @ 0.795% Ni from 202m
§ 12NLJC004: 2m @ 0.636% Ni from 250m
§ 10NLJC0132: 37m @ 0.477% Ni from 205m
ü Including 1m @ 1.02% Ni from 212m
ü 1m @ 0.835%Ni from 206m
ü 1m @ 0.822% Ni from 209m
ü 1m @ 0.766% Ni from 205m
§ LJPR0084: 3m @ 0.649%Ni from 15m
§ LJPA0145:
ü 1m @45.4g/t Au from 44m
ü 3m @ 9.84g/t Au from 42m
Page 14 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
Pride of Elvire WA:
• The tenements surround the Mt. Elvire homestead approximately 210km north of
Southern Cross in Western Australia.
• Encouraging historical gold results include:
Significant Historical Intercepts from Drilling for Gold:
§
§
§
§
ME 30: 10m @ 23.2g/t Au from 17m
ME 22: 2.45m @ 9.29g/t Au from 0m
ME 31: 1m @ 144g/t Au from 15m
ME 21: 2.14m @ 1.77g/t Au from 0m
Significant Historical Rock chip results:
• 6754220mN, 757460mE: 215.3g/t Au
• 6754220mN, 757460mE: 179.7g/t Au
• 6759560mN, 757500mE: 43g/t Au
• 6759700mN, 757300mE: 30g/t Au
• 6756500mN, 757120mE: 24.4g/t Au
• 6759560mN, 757500mE: 14.5g/t Au
• 6756500mN, 757120mE: 5.42g/t Au
• 6756500mN, 757120mE: 3.33g/t Au
To learn more, please visit: www.vertexminerals.com
Stay up to date with the latest news by connecting with VTX on LinkedIn and X.
Competent Persons Statement
The information in this report that relates to the Reward Mineral Resource estimate is based on information
compiled by Mr. Troy Lowien, who is a full-time employee of Groundwork Plus. Mr. Lowien is a member of the
Australasian Institute of Mining and Metallurgy (FAusIMM), and has sufficient experience which is relevant to
the style of mineralisation and type of deposits under consideration and to the activity which he is undertaking
to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of
Exploration results, Mineral Resources and Ore Reserves”. Mr. Lowien consents to the inclusion of the data
contained in relevant resource reports used for this announcement as well as the matters, form and context in
which the relevant data appears.
The information in this report that relates to Exploration Results, Exploration Targets and the Hargraves and Red
Hill Resource Estimates is based on information compiled by Mr. Roger Jackson. Mr. Jackson is a Director and
Shareholder of the Company, who is a Fellow of the Australasian Institute of Mining and Metallurgy (FAusIMM),
Fellow of the Australasian Institute of Geoscientists and a Member of Australian Institute of Company Directors.
Mr. Jackson has sufficient experience which is relevant to the style of mineralisation and type of deposits under
consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012
Edition of the “Australasian Code for Reporting of Exploration results, Mineral Resources and Ore Reserves”. Mr.
Jackson consents to the inclusion of the data contained in relevant resource reports used for this announcement
as well as the matters, form and context in which the relevant data appears.
Page 15 of 16
Vertex Minerals Ltd Quarterly Activities Report – December 2023
JORC Compliance Statements
This website contains references to Mineral Resource estimates, which have been extracted from previous ASX
announcements. These include announcements made by Peak Resources Ltd (ASX:PUA), the parent company of
VTX prior to the Company’s separate listing in 2022. The Resource estimate for the Reward deposit was
announced by Vertex on 23 November 2022.For full details of Exploration Results in this release that have been
previously announced, refer to those announcements.
The Company confirms that it is not aware of any new information or data that materially affects the information
included in the said announcements, and in the case of estimates of Mineral Resources, that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcements
continue to apply and have not materially changed. The Company confirms that the form and context in which
the Competent Persons’ findings are presented have not materially modified from the original market
announcements.
Forward Looking Statements and Important Notice
This report contains forecasts, projections and forward-looking information. Although the Company believes that
its expectations, estimates and forecast outcomes are based on reasonable assumptions it can give no assurance
that these will be achieved. Expectations and estimates and projections and information provided by the
Company are not a guarantee of future performance and involve unknown risks and uncertainties, many of which
are out of Vertex Minerals’ control.
Actual results and developments will almost certainly differ materially from those expressed or implied. Vertex
Minerals has not audited or investigated the accuracy or completeness of the information, statements and
opinions contained in this announcement. To the maximum extent permitted by applicable laws, Vertex Minerals
makes no representation and can give no assurance, guarantee or warranty, express or implied, as to, and takes
no responsibility and assumes no liability for the authenticity, validity, accuracy, suitability or completeness of,
or any errors in or omission from, any information, statement or opinion contained in this report and without
prejudice, to the generality of the foregoing, the achievement or accuracy of any forecasts, projections or other
forward looking information contained or referred to in this report.
Investors should make and rely upon their own enquiries before deciding to acquire or deal in the Company’s
securities.
On behalf of the Directors
Roger Jackson
Executive Chairman
31 January 2024
Page 16 of 16
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Vertex Minerals Ltd
ABN
Quarter ended (“current quarter”)
68 650 116 153
31 December 2023
Consolidated statement of cash flows
Current quarter
$A’000
Year to date (6
months)
$A’000
53
53
(57)
(59)
(b) development
-
-
(c) production
-
-
(d) staff costs
-
-
(166)
(400)
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
(a) exploration & evaluation
(e) administration and corporate costs
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
-
-
1.5
Interest and other costs of finance paid
(5)
(5)
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other (provide details if material)
-
-
1.9
Net cash from / (used in) operating
activities
(174)
(412)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
(306)
(776)
(d) exploration & evaluation
(190)
(562)
(e) investments
-
-
(f)
-
-
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Current quarter
$A’000
Year to date (6
months)
$A’000
Proceeds from the disposal of:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
-
2.6
Net cash from / (used in) investing
activities
(496)
(1,338)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
-
1,668
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
-
(140)
3.5
Proceeds from borrowings
-
197
3.6
Repayment of borrowings
(15)
(20)
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
-
-
3.10
Net cash from / (used in) financing
activities
(15)
1,705
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
1,236
596
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(174)
(412)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
(496)
(1,338)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
(15)
1,705
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
Current quarter
$A’000
Year to date (6
months)
$A’000
4.5
Effect of movement in exchange rates on
cash held
-
-
4.6
Cash and cash equivalents at end of
period
551
551
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
551
1,236
5.2
Call deposits
-
-
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
551
1,236
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
54
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
83
Current quarter
$A'000
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
6.1 Payment of director fees in accordance with disclosed consulting agreements
6.2 Payment to directors of additional consulting fees associated with exploration and
evaluation activities on terms consistent with the disclosed consulting agreements.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
197
197
7.1
Loan facilities
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
7.1 $197,000 loan provided by Caterpillar Financial Australia Limited for a 3 year period at
7.5% per annum, maturing on 15 September 2026. The loan is secured against an item of
equipment.
8.
Estimated cash available for future operating activities
$A’000
8.1
Net cash from / (used in) operating activities (item 1.9)
(174)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(190)
8.3
Total relevant outgoings (item 8.1 + item 8.2)
(364)
8.4
Cash and cash equivalents at quarter end (item 4.6)
551
8.5
Unused finance facilities available at quarter end (item 7.5)
8.6
Total available funding (item 8.4 + item 8.5)
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
551
1.51
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Yes.