Quarterly Activities and Cash Flow Reports 30 June 2026
Released
Released
Announcement PDF
ABN 68 650 116 153
ASX ANNOUNCEMENT
31 July 2026
QUARTERLY ACTIVITIES REPORT
FOR THE PERIOD ENDED 30 JUNE 2026
HIGHLIGHTS FOR QUARTER
Operations - Underground Mining
• Development-focused quarter, with rehabilitation of Declines 1, 2 and 3 continuing
to open the lower levels for bottom-up long hole stoping.
• Decline 2 rehabilitation was completed during the quarter.
• Decline 3 flatback Lift 2 was completed, including rehabilitation and backfilling, ahead
of the first full trial of long hole open stoping on the Mica 1 seam.
• Airleg stoping targeting the high-grade Paxtons Reef advanced across the 671 and
677 levels, both north and south of the Reward shaft.
• Second Aramine tele-remote loader on site and fully operational underground; with
a second Bird underground truck in transit from South Africa.
• New Muki Jumbo rails delivered to enable narrower development drives; Muki LHBP
narrow-vein long hole rig ordered and on track for site and stoping in October 2026.
• DA modification to vary work and blasting hours progressing with Bathurst Regional
Council, with a determination expected mid-August 2026.
Processing
• Gravity-only processing plant continued to operate on underground ore with gold
production in line with the current mine plan.
• Mill recovery improved to 81% in June 2026, with gold sold in June (113 oz)
representing a monthly record for Vertex. This recovery is strong given the lower
grade development material fed to the mill.
Corporate
• Appointment of Bruce McInnes as Executive Chairman, with Roger Jackson
transitioning to Executive Director.
• Completion of the $9 million convertible loan funding (29 June 2026), with an entity
related to Executive Chairman Bruce McInnes investing $115,000.
• Launch of a Share Purchase Plan (1 July 2026) to raise a target of $2.50 million.
Tenements and Exploration
• No exploration field activities were undertaken during the quarter, with the
Company’s focus remaining on underground development and production.
• A new structural geology model has been completed and incorporated into an
updated block model for the Mine. Following completion of an external audit, an
updated Resource will be released.
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 2 of 26
Overview
Vertex Minerals Limited (“Vertex” or “the Company”) is pleased to present its Quarterly
Activities Report for the quarter ended 30 June 2026.
The June 2026 quarter was a period of underground development and decline rehabilitation
for Vertex, alongside a number of significant corporate developments. Consistent with the
current Reward mine plan1, the Company prioritised the rehabilitation of Declines 1, 2 and 3
to open access to the lower levels, from which bottom-up long hole stoping is scheduled to
commence in October 2026. On the corporate front, the Company appointed Bruce McInnes
as Executive Chairman, settled the $9 million convertible loan facility, and after quarter end,
launched a share purchase plan.
Gold production during the June 2026 quarter was lower than the March 2026 quarter,
consistent with the current mine plan, as ore feed was sourced predominantly from
development material and airleg stope ore, ahead of the commencement of long hole
stoping.
The quarterly production information is shown as follows:
Quarter Ended
(unaudited)
Gold
Produced
(oz)
Gold Sold
(oz)
December 2025 123 118
March 2026 284 245
June 2026 195 217
Table 1: Gold production results from the Reward Mine, per quarter, rounded to the nearest ounce.
Vertex Minerals Executive Chairman, Bruce McInnes, commented:
“Since joining Vertex as Executive Chairman during the quarter, my focus has been on
supporting the team as the Reward Gold Mine works through a development-intensive phase
of its transition to a mechanised, long hole stoping operation. The quarter was, by design,
targeted towards underground development and rehabilitation rather than production, as
the Company advances the declines to the lower levels ahead of the planned commencement
of long hole stoping in October 2026."
"During the quarter the Company continued to open and advance multiple mining fronts, with
airleg stoping progressing on the Paxtons Reef across the 671 and 677 levels, Decline 3
flatback Lift 2 completed, and the second Aramine tele-remote loader coming into operation."
1
(ASX:VTX) announcement dated 3 January 2024, ‘Reward Gold Project PFS demonstrates strong economics
and a robust base for future growth’.
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 3 of 26
"The rehabilitation of the declines remains the critical path to production. The underground
workings have been submerged for approximately 14 years and, when dewatered, required
extensive ground support. The team continues to prioritise rehabilitation of Declines 1, 2 and
3, which will progressively deliver higher-grade ore to the plant as stoping ramps up."
"On the corporate front, the $9 million convertible loan facility announced in March was
completed during the quarter, and after quarter end, the Company launched a Share
Purchase Plan. These initiatives strengthen Vertex’s balance sheet and support the continued
development of the Reward Gold Mine."
"Looking ahead, the focus is on completing decline rehabilitation, commencing the first trial
of long hole open stoping and progressing the updated Mineral Resource estimate. We also
await the determination of our development consent modification from the Bathurst regional
council, which is expected in mid-August 2026. I look forward to working with the other board
members and the team to deliver the next phase of Vertex's growth."
Operations
Reward Gold Mine (Hill End, NSW)
Background
The Hill End Gold Project is located in the Central Tablelands of New South Wales,
approximately 50 kilometres south of Mudgee, within the highly prospective Eastern Lachlan
Fold Belt (Image 1). Vertex holds 155 km² of tenure across five exploration licences, one gold
lease (GL 5846) and ten mining leases (ML 49, 50, 315, 316, 317, 913, 914, 915, 1116 and
1541).
The district has a rich gold mining history, with more than four million ounces historically
produced. Vertex’s ground position spans the Hill End corridor and includes several historic
high-grade mines. Mineralisation within the district is hosted within multiple laminated
quartz vein systems, with the Lady Belmore Reef and the adjacent Mica vein systems forming
the principal structures currently being developed.
The cornerstone of the Company’s development strategy is the Reward Gold Mine (Image 2),
a high-grade underground operation accessed via the existing 640 Level portal.
The Reward Gold Mine benefits from substantial existing infrastructure - a permitted
processing plant site, established portal, ventilation and services, permitted residue storage,
and road access. Together, these features provide a strong platform for Vertex’s transition
from explorer to producer.
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 4 of 26
Image 1: Map of the Hill End Project Area
Image 2: Reward Gold Mine (Northwest Looking)
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 5 of 26
Work completed during the quarter and results
During the June 2026 quarter, activities at the Reward Gold Mine were directed toward
advancing underground development and the rehabilitation of Declines 1, 2 and 3, expanding
available airleg mining fronts, and commissioning additional fleet in preparation for the
commencement of long hole stoping. Ore feed during the quarter was predominantly
sourced from development material, consistent with the current mine plan.
Development activities
During the quarter, development activities focused on the rehabilitation of Declines 1, 2 and
3, which will form the basis for production at the Reward Gold Mine over the coming years.
Development advanced 78 metres in April, 88 metres in May and 57 metres in June. In
addition, 42 metres (April), 33 metres (May) and 52 metres (June) of decline rehabilitation
was completed, comprising cutting, meshing and bolting of the decline backs and walls.
The mine also continued to advance airleg development and stoping. Airleg stoping targeting
the high-grade Paxtons Reef advanced across the 671 and 677 levels, with stopes identified
both to the north and south of the Reward shaft. The expansion of available mining fronts
remains a critical component of the Company's strategy to increase overall production rates
and reduce reliance on any single working area. During the quarter, development also
advanced on the remaining cuts required to break through at the 677 Paxtons South Block
and the 677 & 683 Paxtons North Block, with a potential extension identified at the North
Block.
As a result of the progress made during the quarter, Decline 1 had approximately 100 metres
of rehabilitation remaining at quarter end, and Decline 2 reached full rehabilitation (Image
3(a)). The second lift of the Decline 3 mining front was also completed, including
rehabilitation and backfilling. The area is now being prepared for cable bolting, with an air-
leg slot rise to be mined on the Mica 1 lens only, ahead of the first trial of long hole open
stoping. A modified jumbo will carry out the long hole drilling in the interim, until the
dedicated Muki long hole rig arrives (expected in October 2026) (Image 3(b)).
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 6 of 26
Image 3a: Status of the Reward Mine Schedule.
Image 3b: Planned mining activity for July, including airleg stoping of the 671 and 677 levels.
Operational and Strategic Changes
During the quarter, Vertex continued to implement a series of operational initiatives at the
Reward Gold Mine that are designed to increase development grades, expand mining fronts
and progress the transition to mechanised long hole stoping.
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 7 of 26
The following key initiatives were progressed during the quarter:
• Increase to monthly development
As part of its ongoing strategy to increase development grades and reduce dilution
when mining the narrow, high-grade gold veins, the Company reduced development
drive dimensions at the Reward Gold Mine by approximately 20% during the quarter.
By adjusting the drive profile to more closely match the width of the veins, less waste
material is excavated per metre of advance, so that the material mined more
accurately reflects the true grade of the vein. To support the narrower profile, new
Muki jumbo rails were delivered during the quarter and are being fitted to the
Company's existing Epiroc T1D and Atlas Copco H104 jumbo drills, with fitting to be
completed in July 2026 by a specialist fitter from Peru.
Permitted firing times were also modified during the quarter, with blasting moved to
the end of shift to provide additional available mining time per shift.
Fleet capacity at the Reward Gold Mine was also increased to match the growing
number of active mining fronts. The second Aramine tele-remote loader arrived on
site during the quarter and is fully operational, and a second Bird underground truck
is in transit from South Africa, with delivery expected in late August 2026 to remove
haulage bottlenecks.
Vertex has also ordered a Muki LHBP narrow vein long hole production drilling rig
from Resemin, which will provide accurate blast hole drilling within the new smaller
drive dimensions and target stoping widths of approximately 1.2 metres, similar to
the current airleg mining. Construction of the rig is scheduled for completion in mid-
September 2026, and it remains on track to be on site and available for stoping in
October 2026 (Image 4).
Image 4: Muki Production Drilling Rig, to be used at the Reward Gold Mine
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 8 of 26
• Increasing Mining Grade
Alterations to the mine schedule continued to focus on improving development
grades. The Company advanced its airleg mining strategy during the quarter,
operating multiple airleggers targeting high-grade gold stopes on the Paxtons Reef
across the 671 and 677 levels, both north and south of the Reward shaft.
A further high-grade airleg stope on the 677 sublevel is scheduled to come into
production in July 2026, adding another high-grade mining front and contributing
higher-grade ore to the processing plant. Airleg activities experienced some delays
during June 2026 while platforms were established around scrapers and passes on
level; however, both airleg production stope fronts were subsequently brought into
full production in early July 2026.
• Processing Plant Optimisation
The gravity-only processing plant continued to operate on underground ore during
the quarter. No material changes to the processing flowsheet occurred during the
June 2026 quarter.
• Mine Planning and Scheduling Improvements
The Company's mine planning team continued to optimise development, mine
grades, mining techniques, backfill strategies and production scheduling,
incorporating the new structural geology model completed during the quarter.
Scheduling improvements continued during the quarter, increasing the number of
production mining fronts available in the Life of Mine plan and providing greater
operational flexibility. These included a centre retreat mining sequence accessed
from Decline 2 on the 600 Level, which establishes access for mining below the
current known resource.
• Work and Blasting Hours - Development Application Modification
The current restrictions around work hours and blasting times have been identified
as significant factors limiting available underground working hours at the Reward
Gold Mine. The Company's DA modification to vary the working and blasting hours
for the Reward Gold Mine, submitted during the March 2026 quarter, remains before
Bathurst Regional Council, with a determination expected in mid-August 2026.
Approval of this DA modification would materially increase available underground
mining time at the Reward Gold Mine and accelerate the production ramp-up
trajectory toward the mine's nameplate capacity.
Processing and Gold Production
Gold production at the Reward Gold Mine was lower during the June 2026 quarter than prior
quarters, which is consistent with the current mine plan as ore feed was sourced
predominantly from development ore and airleg stope ore, ahead of the commencement of
long hole stoping.
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 9 of 26
The following table summarises gold production and sales performance for the June 2026
quarter:
Month
(unaudited)
Gold
Produced
(oz)
Gold Sold
(oz)
Gross
Revenue ($)
Gold on
Hand (oz)
April 2026 39 53 354,912 29
May 2026 63 51 326,136 41
June 2026 93 113 674,151 21
QUARTER TOTAL 195 217 1,355,199
Table 2: Gold production results from the Reward Mine during the June 2026 quarter, by month
April 2026
During April 2026, all ore processed was sourced from development ore, with no airleg or
jumbo flatback stopes online during the month, consistent with the current mine plan.
Production was therefore lower than March, as expected.
Gold sold in April 2026 was 53 oz, with 29 oz of gold on hand and available for sale at the end
of the month.
Development remained the focus during the month, with 78 metres of advance development
and a further 42 metres of development rehabilitation completed. Decline 3 flatback Lift 2
commenced, with ore to begin processing in July (Image 5). Development of two new airleg
stopes targeting the high-grade Paxtons Reef on the 671 and 677 levels also commenced
during April, and the second Aramine tele-remote loader arrived on site and was
commissioned underground.
Image 5: Long section through the Decline 3 flatbacks
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 10 of 26
May 2026
Gold sold in May 2026 was 51 oz, with 41 oz of gold on hand and available for sale at the end
of the month. Production during May was lower, as expected under the current mine plan,
with higher-grade ore from airleg stopes beginning to be processed towards the end of the
month.
Development remained the focus during May, with 88 metres of advance development and
a further 33 metres of development rehabilitation completed. Rehabilitation of the declines
continued, with Decline 1 having 115 metres of rehabilitation remaining, Decline 2 having
approximately 50 metres remaining, and Decline 3 having approximately 6 metres of flatback
development remaining, before the first full trial of long hole open stoping could commence.
June 2026
Production during June 2026 continued to be sourced from development ore and airleg stope
ore, reflecting the planned emphasis on decline rehabilitation and development ahead of the
commencement of long hole stoping.
Gold produced in June 2026 was 93 oz and gold sold was 113 oz, a monthly record for Vertex,
generating gross revenue of approximately $674,151 for the month. Mill recovery improved
to 82% during June 2026, which was a positive result given that the plant continued to
process lower-grade development ore.
Processing and Underground Mining
The Reward gravity-only processing plant continued to operate on underground ore
throughout the June 2026 quarter, with feed comprising predominantly lower-grade
development material. While the plant is capable of gold recoveries of up to 95%, recoveries
during the quarter reflected the lower-grade feed profile.
Daily operational time at the plant was maintained at approximately 11 hours, following the
extension from 9 to 11 hours implemented in the prior quarter through engineered start-up
and shutdown procedures. This continues to support greater utilisation of plant capacity.
Plant Operational Hours
During the March 2026 quarter, the Company submitted an application to Bathurst Regional
Council to vary the approved working and blasting hours at the Reward Gold Mine, which if
approved would materially increase available underground mining time.
During the June 2026 quarter, there was no change to the status of the application, which
remained under assessment by Bathurst Regional Council.
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 11 of 26
Hargraves Gold Project (Hill End, NSW)
Background
The Hargraves Project is located approximately 35 kilometres north of Hill End in the Central
Tablelands of New South Wales, within the highly prospective Eastern Lachlan Fold Belt. The
project comprises two granted exploration licences (EL 6996 and EL 9485) covering the
historical Hargraves Goldfield. The area has a rich mining history, with more than 1.4 million
ounces of gold historically produced from reef and alluvial workings.
Hargraves hosts a JORC-compliant Mineral Resource of 2.3 million tonnes at 2.4 g/t Au for
178,000 ounces (refer page 18 of this report). Its proximity to Hill End positions Hargraves as
a logical potential satellite ore source, supporting the Company’s strategy of developing Hill
End as a centralised processing hub.
Work completed during the quarter
No work was completed during the quarter for the Hargraves Gold Project.
Taylor Rock Project
Background
The Taylor Rock Project (E63/2058) lies on the southeastern margin of the Lake Johnston
Greenstone Belt in Western Australia, approximately 190 km southwest of Kalgoorlie. The
geological setting is highly prospective, with historic drilling identifying pegmatite swarms
that may host lithium-bearing spodumene, as well as nickel sulphide potential from past
exploration campaigns by Norilsk Nickel.
Image 6: Map of the Taylor Rock Project
Work completed during the quarter
No work was completed during the quarter for the Taylor Rock Project.
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 12 of 26
Pride of Elvire Project
Background
The Pride of Elvire Project (E77/2651, ~51 km²) is located in the Mt. Elvire greenstone belt in
Western Australia, approximately 210 km north of Southern Cross. The project area is
historically known for small-scale gold mining, and previous explorers have undertaken
stream, soil and rock chip sampling, as well as RAB and RC drilling.
Image 7: Map of the Pride of Elvire Project
Work completed during the quarter
No work was completed during the quarter for the Pride of Elvire Project.
Tenement Acquisition and Tenure Update
Tenement Update
No mining or exploration tenements were acquired or disposed of during the June 2026
quarter. All tenements held by the Company remain current and in good standing.
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 13 of 26
The Company’s tenement holdings were unchanged during the quarter. Dun Dun (EL9868),
awarded in the prior quarter, together with the Company’s other exploration licences along
the Hill End-Hargraves trend, remains in good standing and available for future exploration.
A full list of tenements held at 30 June 2026 is set out in the ASX Additional Information
section of this report.
Corporate
Board and Management
On 18 June 2026, Mr Bruce McInnes was appointed as Executive Chairman and a Director of
the Company. Concurrently, Mr Roger Jackson transitioned from Executive Chairman to
Executive Director and remains employed by the Company, working alongside Mr McInnes to
ensure continuity of leadership during the transition.
Mr McInnes is an accountant by profession and brings extensive corporate transaction
experience and regional knowledge of the Central West of NSW, having previously served as
Executive Chairman of Vango Mining Limited, which merged with Catalyst Minerals Limited.
Terms of Mr McInnes’ remuneration and duties can be found within the Company ASX release
dated 18 June 2026.
Funding and Financial Position
During the June 2026 quarter, Vertex undertook the following funding initiative to strengthen
the Company’s balance sheet and to support the development of the Reward Gold Mine.
Completion of $9 Million Convertible Loan Funding
On 29 June 2026, Vertex announced that, with Vert Capital Pty Ltd acting as lead manager, it
had completed and received funds for the Company's additional convertible loan facilities
totalling $9 million (as announced on 25 March 2026). An entity related to the Company's
Executive Chairman, Mr Bruce McInnes, participated in the raising and invested $115,000.
Subject to shareholder approval, the convertible loans (including 10% per annum interest
accrued to the maturity date) will convert into fully paid ordinary shares at the lesser of $0.14
and the Company's 5-day VWAP at the time of conversion, with one free attaching listed VTXO
option (exercise price $0.15, expiring 17 July 2027) for every three shares issued.
Share Purchase Plan (Subsequent to Quarter End)
Subsequent to quarter end, on 1 July 2026, the Company launched a Share Purchase Plan
(SPP) to raise a target of $2.5 million (before costs). Eligible shareholders with a registered
address in Australia or New Zealand as at the record date of 30 June 2026 are eligible to apply
for up to $30,000 of shares at an issue price of $0.10 per share, with the maximum number
of shares to be issued under the Plan being 85,982,370.
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 14 of 26
Investor Relations
The Company’s Executive Director, Mr Roger Jackson, presented at the NSW Mining
Investment Forum on 28 April 2026. The presentation provided an overview of Vertex
Minerals’ operations and strategy, with a particular focus on the Reward Gold Mine and the
Company’s transition into underground production.
Financial
As at 30 June 2026, the Company’s cash position and quarterly cash flows are set out below.
Vertex’s expenditure during the Quarter was as follows:
Item $ (‘000s)
Cash Balance at beginning of Quarter 1,628
Receipts from customers 1,356
Production Costs (894)
Staff Costs (1,010)
Administration and Corporate Costs (958)
Interest and Other Costs of Finance (1)
Exploration and Evaluation (57)
Property, plant and equipment (5,188)
Proceeds from Exercise of Options 4
Proceeds from Borrowings 9,000
Repayment of borrowings (885)
Transaction Costs Related to Loans And Borrowings (555)
Cash Balance at End of Quarter 2,440
ASX Additional Information
The Company provides the following information pursuant to ASX Listing Rule requirements:
1. ASX Listing Rule 5.3.1: Exploration and Evaluation Expenditure spend during the quarter
was $56,883. Full details of exploration activity during the 30 June 2026 quarter are set
out in this report.
2. ASX Listing Rule 5.3.2: The Company confirms that mining production and development
activities occurred during the quarter at the Reward Underground Gold Mine. Ore
extraction and processing were undertaken on a campaign basis through the gravity-only
processing plant, with development and airleg stoping activity across multiple mining
fronts during the quarter.
Expenditure on mining production and development activities during the quarter totalled
$6.08 million, comprising:
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 15 of 26
a. $0.89 million in operating production expenditure (refer Appendix 5B item 1.2(c)),
which includes mining, haulage, processing and site overhead costs; and
b. $5.19 million in mine development and capital works, relating primarily to
underground development, maintenance of surface infrastructure, and continued
optimisation of the gravity-only gold plant.
Gold Production Summary (unaudited)
Metric
December 2025
Quarter
March 2026
Quarter
June 2026
Quarter
Development rehab (m) 146 161 127
Development advance (m) 149 115 223
Ore mined (t)1
5,241 6,038 6,918
Ore processed (t)2
to gravity 2,892 3,861 3,180
Waste to fill (t)3
3,897 3,267 3,617
Gold recovered (oz) 123 284 195
Gold sold (oz) 118 245 217
Average gold price realised ($/oz) 6,362 7,006 6,245
1
All production and processing data is subject to final metallurgical reconciliation and assay confirmation.
2
Ore processed to gravity represents the actual crushed ore sent to the gravity plant for processing after
the reject rock has been rejected by the ore sorter.
3
Waste to fill represents crushed rock rejected by the ore sorter to be returned to the mine for backfill.
4
All-in Sustaining Cost (AISC) metrics have not been disclosed for the quarter, as operations have not yet
reached steady-state production and the processing profile was materially impacted by the level of low-
grade stockpile and development material.
ASX Listing Rule 5.3.3: During the June 2026 quarter, the Company did not acquire any
mining or exploration tenements.
The Company did not dispose of any mining or exploration tenements during the quarter.
A full list of mining and exploration tenements held at 30 June 2026 is set out in the
Tenement Schedule below. Interests are held either directly by the Company, through its
subsidiaries, or pursuant to contractual arrangements.
All tenements remain in good standing.
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 16 of 26
Mining tenements held at the end of the Quarter
Tenement Project Status Area Location
EL 5868 Hill End Current 16 Units NSW
EL 6996 Hargraves Renewal Pending 6 Units NSW
EL 9485 Hargraves Current 1 Unit NSW
EL 9564 Hill End Current 2 Units NSW
EL 8289 Hill End Current 1 Unit NSW
EL 9247 Hill End Current 2 Units NSW
EL 9413 Hill End Current 1 Unit NSW
GL 5846 Hill End Current 2.044 ha NSW
ML 49 Hill End Current 1.618 ha NSW
ML 50 Hill End Current 3.02 ha NSW
ML 315 Hill End Current 6.671 ha NSW
ML 316 Hill End Current 8.846 ha NSW
ML 317 Hill End Current 7 ha NSW
ML 913 Hill End Current 22 ha NSW
ML 914 Hill End Current 21.69 ha NSW
ML 915 Hill End Current 13.27 ha NSW
ML 1116 Hill End Current 15.71 ha NSW
ML 1541 Hill End Current 279.2 ha NSW
EPL 12008 Hill End Issued - -
E77/2651 Pride of Elvire Current 51km2 WA
E 63/2058 Taylors Rock Current 57km2 WA
EL 9434 Hill End Current 30 Units NSW
EL 9868 Hill End “Dun Dun” Current 22 Units NSW
Farm-in or Farm-out Agreements entered into during the Quarter
None
Beneficial Percentage Interests Held in Farm-in or Farm-out agreements at the end of the
Quarter
None
3. ASX Listing Rule 5.3.5: Payment to related parties of the Company and their associates
during the quarter was $269,347, in cash. Such payments related to directors’ fees and
consulting fees for both technical and management services.
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 17 of 26
End Notes
The information contained in this announcement related to the Company’s past exploration
results is extracted from, or was set out in, the following ASX announcements which are
referred to in this Quarterly Activities Report:
Date of announcement Name of announcement
3 January 2024 Reward Gold Project PFS demonstrates strong
economics and a robust base for future growth
9 April 2026 Ore Production Update, Reward Gold Mine
28 April 2026 NSW Mining Investment Forum Presentation
7 May 2026 Ore Production Update, Reward Gold Mine
12 June 2026 Ore Production Update, Reward Gold Mine
18 June 2026 Appointment of Executive Chairman
29 June 2026 Completion of $9M Convertible Loan Funding
14 July 2026 Ore Production Update, Reward Gold Mine
Vertex Minerals Ltd Quarterly Activities Report - June 2026
Page 18 of 26
ABOUT VERTEX
Hill End NSW:
• 14km of Continuous gold lode
• Gold recovers to gravity at +90%
• Most of the line of lode only mined to the water table
• The Hill End Gold project consists of 10 mining leases & 4 Exploration licenses located
in the core of the Hill End Trough on the eastern Lachlan Fold Belt.
• The area was first recognised as a gold centre in 1851 with a number of mining
operations established over the following 50 years
• Gravity Plant on site
• Fully permitted Gravity processing licence
• Reward Underground High-Grade Gold Mine - mine ready
Reward Gold Mine: 2.0g/t reporting cutoff grade
Hargraves: 0.8 g/t reporting cutoff grade (ASX Announcement 29 May 2020).
Red Hill: 0.5 g/t per b