UPDATE - Reward Gold Mine Project Update
Released
Released
Announcement PDF
VVTXVVVVV
ASX:VTX
ASX ANNOUNCEMENT 9 JULY 2025
UPDATE - Reward Gold Mine Project Update (9 July 2025)
Vertex Minerals Limited (ACN 650 116 153) (Company) earlier released an announcement titled “Reward Gold Mine
Project Update” dated 9 July 2025 (Release).
In the Release, VTX referred to its existing Mineral Resource Estimate but there was no Mineral Resource category
breakdown or Competent Person’s statement.
To comply with the JORC Code and ASX Listing Rules, the Company is updating the Release with a Mineral Resource
category breakdown and Competent Person’s statement.
The updates are reported on pages 7 and 8 of the following updated Release.
This announcement has been approved by Roger Jackson, Executive Chairman.
Further Information:
Roger Jackson, Executive Chairman
roger@vertexminerals.com.au
Follow Vertex Minerals on LinkedIn
Vertex Minerals Limited
ASX Code: VTX
ABN: 68 650 116 153
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
1
ASX:VTX
ASX ANNOUNCEMENT 9TH JULY 2025
REWARD GOLD MINE PROJECT UPDATE
Moving to high grade gold production
HIGHLIGHTS:
•
Operational Milestones
✓ VTX remains firmly on track to commence production of high-grade ore from the
underground mine in the forthcoming weeks.
✓ Transformer and cabling for the installation of 11kV high voltage underground power system
on site with installation commenced.
✓ Preparations for the underground mine startup up progressing as planned and stripping of
the main access is completed.
✓ New Aramine L350D has departed France for the journey to Hill End. Arrival in Orange NSW
expected in by 26th August where it will be fitted with an RCT remote control system for open
stoping operations.
✓ Mining the Reward Gold Mine – Resource 225kozs at 16.7g/t (VTX ASX Announcement 21 June 2023).
Classification
Cut-off
Tonnes
Au (g/t)
Indicated
4
141,000
15.54
70,500
Inferred
4
278,000
17.28
154,700
Total
4
419,000
16.72
225,200
Ounces
✓ Weekly Gold production Oz’s from Stockpiles improving with depth in the stockpiles, with
coarser particle size and better process throughput experienced.
•
Mine start up
✓ Fan chambers have been excavated to provide secondary ventilation for production
activities, exploration drilling and the future southern access toward the Fosters’ exploration
target.
✓ Primary ventilation fan has been installed and bulkhead completed.
✓ High voltage surface substation has been installed.
✓ High voltage cabling installation commences next week, with power up of the system
scheduled for 28 July 2025.
✓ Stripping of the main access is completed with the final elements of ground support (approx.
30m) to be completed before power cable installation starts next week.
✓ Cable bolts installed for the intersection of Lady Belmore exploration drive with first cut
drilled out and ready to charge.
✓ Development Jumbo #1 (Epiroc T1D) is exceeding performance expectations.
✓ Dewatered of declines well underway.
✓ Mine schedule for FY26 finalised.
✓ First airleg stope secondary vent installed and specialty equipment on site to start first air
leg stope.
✓ First long hole stope planned for August. High grade from airleg and longhole stopes to
complement larger tonnage from development ore headings.
2
•
People that have been onboarded
✓ 2x Drill Fitters and Heavy diesel fitter.
✓ Process superintendent commences next week.
✓ Full Tech team started including mine surveyor this week.
✓ Have back-to-back airleg miners for stoping.
✓ Full underground and mill crews.
•
Improvements to plant
✓ DSM screen installed to improve product delivery to Wilfley Table.
Gemini table improvements with new tabletop and gearbox improving final concentrate grade to over
20% gold (suitable for direct smelting to Dore on site).
✓
•
Process water pump upgrade improving ore washing and Tomra performance.
Revised mine plan and schedule completed and ready to implement
• Updated Reward Gold mine mining plan and mine schedule completed.
• Adding a high-grade long hole stope upfront to be mined concurrently with the high grade
airleg stope.
Vertex Minerals Limited (ASX:VTX, Company) is pleased to announce that the underground mining
operation is on track to be producing high grade gold feed to the recently commissioned gravity
gold plant in the coming weeks.
Vertex Director Declan Franzmann commented: “It is great to see all the elements of re-developing
the underground mine and processing facility coming together so rapidly. The most pleasing aspect
is our success in employing an incredible team of people to run the operation and all credit to
management for developing great “esprit de corps” and a single sense of purpose as we push to full
production.”
Figure 1 – High voltage (415V to 11kV) transformer installed next to power station at the Reward Gold plant
3
Figure 2 - 110kW primary ventilation fan installed and ready for power
Figure 3 The underground substation cuddy completed
4
Figure 4 - The Lady Belmore quartz vein with bored out ready to charge
Figure 5 Mica Lense declines. One of three gold bearing declines being dewatered.
As previously announced, the startup mine schedule includes mining 2,075 tonnes at 17.8 g/t Au
from a developed airleg stope block. The planned stope width is the same as the interpretation of
the mineralisation. (Refer to Table 1 in Appendices 1) (VTX ASX announcement 26/06/23).
Given this stope will take some time to extract, the Vertex geology and Mining Team have
5
additionally brought forward a very high-grade long hole stope to commence mining in August as
well. Further optimisations to the mining schedule will continue to be made.
This stope can be exploited as soon as services have been established. The mining crews have done
a great job in the access drive to make room for the services (11kV cable, water and air lines) while
improving accessibility for the mobile mining equipment selected for the Project.
Figure 6 – Back height increased in the Amalgamated Adit to hang the High Voltage 11kV cables and services.
Figure 7. T1D jumbo operational and bolting the main access.
6
Figure 8 – Upgrade of 25-year-old steel sets at the Amalgamated Portal.
This announcement has been approved by the Vertex Board of Directors
Further Information:
Roger Jackson, Executive Chairman
roger@vertexminerals.com.au
Follow Vertex Minerals on LinkedIn
Tully Richards, Technical Director
tully@vertexminerals.com.au
7
Vertex Flagship project
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
Commenced gold processing in new Gekko gravity gold plant
100% owned mining operation
No hedge - no secured debt – fully funded
High grade gold resource and reserve 225 ozs at 16.7g/t + more
Inherited AU$25 million of underground development at Reward
1.8m Au ozs historic mining
Reward sits just under the historic Hawkins Hill mine - 435kozs at 309 g/t Au
Production has commenced on stockpiles.
Underground development well underway.
Underground high-grade gold production commencing in weeks
Up to 95% recovery by gravity processes only
Big gold system – 25km + strike
MINERAL RESOURCE ESTIMATE (MRE) FOR THE REWARD GOLD DEPOSIT AT HILL END NOW STANDS
AT 419,000T AT 16.72G/T AU FOR 225,200OZ AU:
Classification
Cut-off
Tonnes
Au (g/t)
Ounces
Indicated
4
141,000
15.54
70,500
Inferred
4
278,000
17.28
154,700
Total
4
419,000
16.72
225,200
Global Mineral Resource estimate for the Hill End & Hargraves Gold Project
Hill End Project Mineral Resource Estimate
Deposit
Classification
Tonnes
(kt)
Grade
Au (g/t)
Contained
Au (koz)
Reward Gold Mine
Indicated
Inferred
Sub Total
141
278
15.5
17.3
71
155
419
16.7
225
1,109
1,210
2.7
2.1
97
80
2,319
2.4
178
413
1,063
1.4
1.8
19
61
1,476
1.7
80
1,663
2,551
8.9
8.6
187
296
4,214
8.7
482
Hargraves Project
Indicated
Inferred
Sub Total
Red Hill Project
Indicated
Inferred
Sub Total
Project Total
Indicated
Inferred
Grand Total
8
COMPETENT PERSON’S STATEMENT
The information in this report that relates to Exploration Results and Exploration Targets is based on
information compiled by Mr. Roger Jackson, a Director and Shareholder of the Company, who is a 25+ year
Fellow of the Australasian Institute of Mining and Metallurgy (FAusIMM), Fellow of the Australian Institute of
Geoscientists (FAIG) and a Member of Australian Institute of Company Directors. Mr. Jackson has sufficient
experience which is relevant to the style of mineralisation and type of deposits under consideration and to
the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the
“Australasian Code for Reporting of Exploration results, Mineral Resources and Ore Reserves”. Mr. Jackson
consents to the inclusion of the data contained in relevant resource reports used for this announcement as
well as the matters, form and context in which the relevant data appear.
FORWARD LOOKING STATEMENTS AND IMPORTANT NOTICE
This report contains forecasts, projections and forward-looking information. Although the Company believes
that its expectations, estimates and forecast outcomes are based on reasonable assumptions it can give no
assurance that these will be achieved. Expectations and estimates and projections and information provided
by the Company are not a guarantee of future performance and involve unknown risks and uncertainties, many
of which are out of Vertex Minerals’ control.
Actual results and developments will almost certainly differ materially from those expressed or implied.
Vertex Minerals has not audited or investigated the accuracy or completeness of the information, statements
and opinions contained in this announcement. To the maximum extent permitted by applicable laws, Vertex
Minerals makes no representation and can give no assurance, guarantee or warranty, express or implied, as
to, and takes no responsibility and assumes no liability for the authenticity, validity, accuracy, suitability or
completeness of, or any errors in or omission from, any information, statement or opinion contained in this
report and without prejudice, to the generality of the foregoing, the achievement or accuracy of any forecasts,
projections or other forward looking information contained or referred to in this report. Investors should
make and rely upon their own enquiries before deciding to acquire or deal in the Company’s securities.
JORC COMPLIANCE STATEMENTS
Where statements in this announcement refer to exploration results which previously been reported, the
Company confirms that it is not aware of any new information or data that materially affects the information
included in the original announcements, and in the case of estimates of Mineral Resources, that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcements
continue to apply and have not materially changed. The Company confirms that the form and context in which
the Competent Person’s findings are presented have not materially modified from the original market
announcements.