Quarterly Activities and Cash Flow Reports 31 March 2026
Released
Released
Announcement PDF
ABN 68 650 116 153
ASX ANNOUNCEMENT
30 April 2026
QUARTERLY ACTIVITIES REPORT
FOR THE PERIOD ENDED 31 MARCH 2026
HIGHLIGHTS FOR QUARTER
Operations - Underground Mining
• Gold production continued to ramp up month on month throughout the quarter, with
total output increasingly significantly compared to the previous quarter (284 oz vs
123 oz)
• All three declines (Decline 1, 2 and 3) are now in low grade ore, with airleggers
operational and targeting high-grade gold stopes in the 671 level.
• Rehabilitation (cutting, meshing and bolting) progressing on Declines 1 and 2, with
jumbo ore stripping continuing in Decline 3.
• Opening of additional mining fronts, including the Paxton Reef.
• Second Aramine loader delivered, providing tele-remote backup capability ahead of
full stoping activities.
• Development Application (DA) modification submitted to Bathurst Regional Council
for 24/7 underground operations.
Processing
• Improvements made to the TOMRA ore sorter, achieving 99.5% recovery of quartz,
with further improvements implemented to capture residual quartz and maximise
mill feed quality.
Corporate
• Appointment of Jim Simpson as Executive Director - Operations.
• Renegotiated existing A$3.0M loan facility (extended term and revised interest) and
negotiated a new A$1.5M loan facility.
• Secured A$9.0 million in new convertible loan funding, committed but being received
post quarter end.
Tenements and Exploration
• Exploration Licence 9868 (EL9868) "Dun Dun" awarded, providing Vertex with
approximately 50 km of contiguous geology along the Hill End-Hargraves trend.
• Five gold-bearing quartz veins are to be targeted at Dun Dun, analogous to the vein
systems currently being mined at the Reward Gold Mine.
Safety
• No lost time injuries recorded during the March 2026 quarter.
• Implementation of additional health and safety policies to proactively identify and
manage risk across all operational areas.
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 2 of 27
Overview
Vertex Minerals Limited (“Vertex” or “the Company”) is pleased to present its Quarterly
Activities Report for the quarter ended 31 March 2026.
The March 2026 quarter represented a period of operational advancement, strategic
restructuring and corporate development for Vertex. The Company continued to ramp up
gold production at the Reward Gold Mine, implementing a series of targeted operational
improvements under the leadership of newly appointed Executive Director of Operations,
Jim Simpson. In addition, Vertex secured critical funding to support ongoing underground
development and production ramp-up at the Reward Gold Mine, while also expanding its
exploration footprint through the award of the Dun Dun Exploration Licence.
Gold production increased steadily throughout the quarter, with gold produced totalling 284
oz, representing a strong quarterly improvement. Compared to previous quarters, this result
is consistent with the progressive ramp-up in mining and processing activities as the
operation advances toward steady-state production, which can be shown as follows:
Quarter Ended
(unaudited)
Gold
Produced
(oz)
Gold Sold
(oz)
September 2025 77 77
December 2025 123 118
March 2026 284 245
Table 1: Gold production results from the Reward Mine, per quarter
Production during the March 2026 quarter was predominantly sourced from development
material and airleg stope ore, with operational focus remaining on the rehabilitation of
Declines 1, 2 and 3, to enable access to planned stoping areas.
Vertex Minerals Executive Chairman, Roger Jackson, commented:
“The March 2026 quarter represented continued forward momentum for Vertex as the
Reward Gold Mine progressed through its production ramp-up phase. Following the
appointment of Jim Simpson as Executive Director of Operations, activities during the period
focused on implementing targeted operational and strategic changes designed to accelerate
the transition to commercial production and advance the mine toward its nameplate
capacity."
"During the quarter, the Company achieved several important milestones, including the
arrival of the second Aramine tele-remote loader, the advancement of airleg stoping activities
targeting high-grade gold in the upper levels, and the commencement of backfilling
operations in the first flatback stope at the base of Decline 3. Gold production rose to 121 oz
in the month of March 2026, and while the operation remains in its ramp-up phase, this
trajectory reflects an expansion of available mining fronts and the ongoing benefits of
rehabilitation work across all three declines."
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 3 of 27
"We have been previously burdened by significant unplanned rehabilitation work in the
declines, which has delayed our access to productive stopes. The underground workings had
been submerged for approximately 14 years, and when dewatered were found to be in far
poorer condition than originally anticipated, requiring extensive ground support. However,
we take safety seriously and are committed to making this mine both productive and safe."
"On the corporate front, we strengthened the Company's balance sheet during the quarter
through the renegotiation of existing debt facilities and the execution of a new A$9 million
convertible loan funding package. These facilities provide the flexibility and headroom
required as we transition the Reward Gold Mine toward steady-state production."
"Looking ahead, our focus is on building momentum through 2026 by increasing stoping
rates, integrating additional ore sources and continuing to de-risk the mine operation. With
multiple mining fronts now established, tele-remote systems commissioned, and a clear
development pathway in place, Vertex is well positioned to deliver continued progress
throughout the remainder of the year."
Operations
Reward Gold Mine (Hill End, NSW)
Background
The Hill End Gold Project is located in the Central Tablelands of New South Wales,
approximately 50 kilometres south of Mudgee, within the highly prospective Eastern Lachlan
Fold Belt (Image 1). Vertex holds 155 km² of tenure across five exploration licences, one gold
lease (GL 5846) and ten mining leases (ML 49, 50, 315, 316, 317, 913, 914, 915, 1116 and
1541).
The district has a rich gold mining history, with more than four million ounces historically
produced. Vertex’s ground position spans the Hill End corridor and includes several historic
high-grade mines. Mineralisation within the district is hosted within multiple laminated
quartz vein systems, with the Lady Belmore Reef and the adjacent Mica vein systems forming
the principal structures currently being developed.
The cornerstone of the Company’s development strategy is the Reward Gold Mine (Image 2),
a high-grade underground operation accessed via the existing 640 Level portal.
The Reward Gold Mine benefits from substantial existing infrastructure - a permitted
processing plant site, established portal, ventilation and services, permitted residue storage,
and road access. Together, these features provide a strong platform for Vertex’s transition
from explorer to producer.
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 4 of 27
Image 1: Map of the Hill End Project Area
Image 2: Reward Gold Mine (Northwest Looking)
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 5 of 27
Work completed during the quarter and results
During the March 2026 quarter, activities at the Reward Gold Mine were directed toward
accelerating the production ramp-up through a combination of underground rehabilitation,
expansion of available mining fronts, deployment of additional fleet, and targeted
operational changes under the leadership of newly appointed Executive Director of
Operations, Jim Simpson.
Development activities
During the quarter, development activities at the Reward Gold Project focused on the
rehabilitation of all three declines which are the basis for production over the next several
years. Works comprising of cutting, meshing and bolting of the decline backs and walls
progressed steadily across Declines 1, 2 and 3 throughout the period. Decline 3 reached a
significant milestone, with rehabilitation advancing sufficiently to enable the
commencement of flatback stoping. The first flatback stope at the base of Decline 3 was
successfully mined and backfilled during March 2026, with the next lift commencing shortly
after quarter end. Jumbo ore stripping also continued in Decline 3 to further advance access
to the lower stope panels.
By quarter end, all three declines had advanced into ore, representing a significant
operational milestone for the Company. While rehabilitation activities continued across
Declines 1 and 2, and jumbo ore stripping progressed in Decline 3, the advancement of all
decline systems into ore signalled the commencement of bottom-up stoping sequences. This
will progressively deliver higher-grade ore to the processing plant as the stoping programme
advances toward the October 2026 commencement date for long hole stoping (Image 3).
In addition to decline rehabilitation activities, the mine continued to open new mining fronts
during the quarter. Mining on the Paxton Reef progressed across four headings on the 640L,
while airleg activities targeting the high-grade Paxton Reef on the 671 Level advanced, with
the first rise on the north front completed ahead of stoping commencement and scrapers
installed on the south front. The expansion of available mining fronts remains a critical
component of the Company's strategy to increase overall production rates and reduce
reliance on any single working area.
Operational and Strategic Changes
Following the appointment of Jim Simpson as Executive Director of Operations in February
2026, Vertex implemented a series of targeted operational and strategic changes at the
Reward Gold Mine, designed to accelerate the transition to commercial production and
progress towards the mine's nameplate capacity in staged approach.
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 6 of 27
Image 3: Status of the Reward Mine Schedule, as of March 2026.
While the mine continues to produce gold and ramp up production, the following key
initiatives were introduced to accelerate the rate of production and optimise performance
across all mine areas:
• Increase to monthly development
During the March 2026 quarter, Vertex implemented a series of changes to increase
monthly development rates and accelerate the progression to stoping. Development
drive dimensions were reduced by approximately 20% to improve development
grades and reduce external dilution to the narrow, high-grade gold veins. To support
this, modified Muki booms were ordered from Resemin (Peru) for the Company's
Epiroc Jumbos. These booms will allow smaller drive sizes, reducing dilution by
greater than 20% for the same cut length, and are expected to be operational at the
Reward Gold Mine in June 2026. Permitted firing times were also modified, with
blasting moved to the end of shift to provide approximately 25% more available
mining time per shift.
Increases were also made to the fleet capacity at the Reward Gold Mine to match the
increasing number of active mining fronts. A second Aramine loader arrived in Sydney
in March 2026 and was undergoing final fit-out of tele-remote systems in Orange,
NSW at the end of the quarter, with delivery to site expected in early May 2026. A
second Bird underground truck was also under construction during the quarter to
provide additional haulage capacity and prevent bottlenecks as stoping activities
ramp up. Lastly, for the purposes of supporting accurate blast hole drilling within the
new smaller drive dimensions, the Company also commenced discussions on the
purchase of a Muki LHBP narrow vein long hole production drilling rig - a separate
Resemin product to the Muki booms ordered earlier in the quarter - which will
directly support improved grade control and production efficiency. Discussions and
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 7 of 27
negotiations remained ongoing at the end of the March 2026 quarter (Image 4).
Image 4: Muki Production Drilling Rig, to be used at the Reward Gold Mine
• Increasing Mining Grade
Alterations were made to the mine schedule to focus on grade rather than volume of
production. The Company progressed its airleg mining strategy during the quarter,
with the mine operating multiple airleggers targeting high-grade gold stopes in the
upper levels. The Paxton Reef on the 671 Level represents one of the principal airleg
targets, with four headings in operation during the quarter. Two additional airleggers
were commissioned during the period to expand the airleg programme.
• Processing Plant Optimisation
Optimisation activities were undertaken during the quarter to support operations at
or near nameplate throughput capacity for the TOMRA plant. Key initiatives included:
▪ modifications to the TOMRA ore sorter screens and feed chutes to increase
sorting accuracy and reduce ore loss; and
▪ installation of cross cut tailings sampler to improve data accuracy and maximise
overall gold recovery.
Through this ongoing optimisation work, the TOMRA ore sorter achieved a better
than 99.5% recovery of quartz. The Company also implemented a system to retrieve
the small fraction of quartz previously missed, ensuring that all material is processed
through the mill.
• Mine Planning and Scheduling Improvements
A mine planner with 35 years of experience was engaged during the quarter to work
alongside the mine team to optimise mining development, mine grades, mining
techniques, backfill strategies, and production scheduling.
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 8 of 27
Scheduling improvements were implemented during the quarter to improve the
number of production mining fronts accessible in the Life of Mine plan.
• 24/7 Underground Operations – Development Application Modification
During the quarter the Company submitted a modification to the Reward Gold Mine
Development Application ("DA") to Bathurst Regional Council to permit 24/7
underground operations. The DA modification was placed on public exhibition during
the quarter and expected to have an outcome later this year.
Approval of this modification would allow the underground operation to operate 24
hours per day, seven days per week, effectively doubling available mining time and
significantly accelerating the production ramp-up trajectory toward the mine's name
plate capacity.
Processing and Gold Production
Gold production at the Reward Gold Mine continued to increase throughout the March 2026
quarter, with each month recording an improvement on the prior month.
Production during the quarter was sourced predominantly from development ore and airleg
stoping activities, with the progressive establishment of additional mining fronts
underpinning the month-on-month growth trajectory.
The following table summarises gold production and sales performance for the March 2026
quarter, together with comparative results for previous quarters:
Month
(unaudited)
Gold
Produced
(oz)
Gold Sold
(oz)
Gross
Revenue
(A$)
Gold on
Hand (oz)
January 2026 79 71 $503,424 13
February 2026 84 85 $608,429 12
March 2026 121 89 $606,248 44
QUARTER TOTAL 284 245 $1,718,101
Table 2: Gold production results from the Reward Mine during the March 2026 quarter, by month
January 2026
During January 2026, gold production of 79 oz was achieved.
Production during the month was sourced from the high-grade 640-Mica Vein-1618N long
hole stope, which had been drilled and fired during December 2025, together with lower-
grade development material from Decline 3 (Image 5).
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 9 of 27
Image 5: Long section through the Decline 3 flatbacks
February 2026
Gold production for February 2026 was 84 oz, generating gross revenue of $608,429,
representing an improvement on January 2026 production results. Production during
February was predominantly from flatback mining whilst also consisting of a mix of
development ore and some airleg stope ore.
March 2026
Gold production for March 2026 was 121 oz - the highest monthly production figure achieved
by the Reward Gold Mine. Gold sold during March was 89 oz, generating gross revenue of
approximately $606,000, with 44 oz of gold on hand and available for sale as at 31 March
2026.
Production during the month was sourced from development ore and airleg stope ore,
reflecting the progressive expansion of available mining fronts and the ongoing
commencement of stoping activity across multiple working areas. The backfilling of the first
flatback stope at the bottom of Decline 3 was completed during March 2026, with the next
lift ready to commence at quarter end.
Processing
The Reward gravity-only processing plant continued to operate on underground ore
throughout the March 2026 quarter. Optimisation activities were ongoing throughout the
period, with a focus on increasing operational uptime, improving throughput consistency,
and maximising gold recoveries across all stages of the process circuit.
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 10 of 27
TOMRA Optimisation
TOMRA technicians attended site during January 2026 to make targeted adjustments to the
ore sorter, with the objective of improving sorting performance in line with the
characteristics of the underground ore feed being processed. Further improvement works
were carried out by TOMRA technicians during the quarter to progressively align the sorter's
operating parameters with the changing underground ore feed from the Reward project. As
noted under the Operational and Strategic Changes section of this release, such adjustments
resulted in the TOMRA ore sorter achieving a better than 99.5% recovery of quartz, reflecting
a significant operational milestone for Vertex.
Plant Operational Hours
Daily operational time at the processing plant was extended from 9 hours to 11 hours during
the quarter through the implementation of engineered start-up and shutdown procedures.
This increase in available processing time supports a greater utilisation of the plant's
capacity.
Hargraves Gold Project (Hill End, NSW)
Background
The Hargraves Project is located approximately 35 kilometres north of Hill End in the Central
Tablelands of New South Wales, within the highly prospective Eastern Lachlan Fold Belt. The
project comprises two granted exploration licences (EL 6996 and EL 9485) covering the
historical Hargraves Goldfield. The area has a rich mining history, with more than 1.4 million
ounces of gold historically produced from reef and alluvial workings.
Hargraves hosts a JORC-compliant Mineral Resource of 2.3 million tonnes at 2.4 g/t Au for
178,000 ounces (refer page 19 of this report). Its proximity to Hill End positions Hargraves as
a logical potential satellite ore source, supporting the Company’s strategy of developing Hill
End as a centralised processing hub.
Work completed during the quarter
No work was completed during the quarter for the Hargraves Gold Project.
Taylor Rock Project
Background
The Taylor Rock Project (E63/2058) lies on the southeastern margin of the Lake Johnston
Greenstone Belt in Western Australia, approximately 190 km southwest of Kalgoorlie. The
geological setting is highly prospective, with historic drilling identifying pegmatite swarms
that may host lithium-bearing spodumene, as well as nickel sulphide potential from past
exploration campaigns by Norilsk Nickel.
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 11 of 27
Image 6: Map of the Taylor Rock Project
Work completed during the quarter
No work was completed during the quarter for the Taylor Rock Project.
Pride of Elvire Project
Background
The Pride of Elvire Project (E77/2651, ~51 km²) is located in the Mt. Elvire greenstone belt in
Western Australia, approximately 210 km north of Southern Cross. The project area is
historically known for small-scale gold mining, and previous explorers have undertaken
stream, soil and rock chip sampling, as well as RAB and RC drilling.
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 12 of 27
Image 7: Map of the Pride of Elvire Project
Work completed during the quarter
No work was completed during the quarter for the Pride of Elvire Project.
Tenement Acquisition and Tenure Update
Dun Dun Exploration Licence Application (EL9868)
On 17 February 2026, Vertex was awarded Exploration Licence 9868 (EL9868), known as the
"Dun Dun" licence. Situated between Vertex's existing "Hill End" (EL5868) and "Hargraves"
(EL6996) tenements, EL9868 provides approximately 50 kilometres of contiguous geology
along the Hill End-Hargraves trend.
Dun Dun hosts historic gold workings underlain by gold-bearing quartz veins associated with
the Hill End Anticline - the same geological structure hosting the Lady Belmore Reef and Mica
vein systems at the Reward Gold Mine. Five distinct veins have been identified at the project
for future exploration:
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 13 of 27
• Northeast Vein - characterised by historic pits and underlay shafts;
• Longmore (Reward/East Intermediate) Vein - 7.5–10 cm wide, gold-bearing where
intersected by faults;
• Dun Dun (Craigend/Main) Vein - 20-30 cm thick, extending over one kilometre along
strike, worked to 106.7 metres depth;
• West Intermediate Vein - associated with historic trenches and pits;
• Southwest Vein - completing the five-vein system.
Image 8: Map of ELA 6978 “Dun Dun”
Corporate
Board and Management
On 3 February 2026, Mr Jim Simpson was appointed as the Executive Director of Operations.
Mr Simpson, who was already a non-executive Director of the Company (refer to
announcement dated 19 December 2025) and transitioned into the executive role to lead the
operational management of the Reward Gold Mine. This appointment represented a
significant step in Vertex's strategy to accelerate the transition to commercial gold
production, with Executive Chairman Roger Jackson handing over day-to-day operational
management to Mr Simpson.
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 14 of 27
Funding and Financial Position
During the March 2026 quarter, Vertex undertook a series of financing transactions to
strengthen the Company's balance sheet and provide resources to support the production
ramp-up at the Reward Gold Mine.
Renegotiated Existing Loan Facility (A$3.0M)
On 11 March 2026, Vertex announced the renegotiation of its existing A$3.0 million loan
facility with RBTN Investments Pty Ltd (formerly Rangwell Boys Pty Ltd). The term of the
facility was extended from seven months to ten months, and the fixed interest amount was
revised to A$360,000 (approximately 14.40% per annum for the 10-month term). Subject to
shareholder approval, RBTN may elect to receive interest and fees in cash or by way of option
bundles comprising listed VTXO options (exercise price A$0.15, expiring 17 July 2027) and
unlisted VTXAN options (exercise price A$0.20, expiring 15 December 2028), or any
combination thereof.
New Loan Facility (A$1.5M)
Also on 11 March 2026, Vertex announced the negotiation of a new A$1.5 million loan facility
with Richsham Nominees Pty Ltd. This facility carries a 10-month term and fixed interest of
A$180,000 (approximately 14.40% per annum). Subject to shareholder approval, the lender
may elect to receive interest and fees in options on the same basis as the RBTN facility.
Vert Capital Pty Ltd acted as manager for this facility and received a management fee of 6.00%
plus GST on funds raised.
New Convertible Loan Funding (A$9.0M)
On 25 March 2026, Vertex announced that it had successfully negotiated $9.0 million in new
convertible loan funding with unrelated sophisticated and professional investors, with Vert
Capital Pty Ltd acting as lead manager.
Subject to shareholder approval, the convertible loans (including accrued interest) will be
converted into fully paid ordinary shares at a conversion price equal to the lesser of A$0.14
and the Company's 5-day volume weighted average price at the time of conversion.
Additionally, for every three shares issued on conversion, investors will receive one free
attaching listed VTXO option (exercise price A$0.15, expiring 17 July 2027).
In the event that shareholder approval is not obtained, the outstanding sum becomes
repayable in full in cash.
Investor Relations
During the March 2026 quarter, the Company’s Chairman, Roger Jackson, presented at the
Blue Ocean Equities Based and Precious Metals Conference and Gold Coast Gold 2026
Conference. The presentation provided an overview of Vertex Minerals’ operations and
strategy, with a particular focus on the Reward Gold Mine and the Company’s transition into
underground production.
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 15 of 27
Financial
As at 31 March 2026, the Company had A$1,628,000 in cash (unaudited).
Vertex’s expenditure during the Quarter was as follows:
Item A$ (‘000s)
Cash Balance at beginning of Quarter 1,498
Receipts from customers 1,719
Production Costs (240)
Staff Costs (1,186)
Administration and Corporate Costs (493)
Interest and Other Costs of Finance (3)
Exploration and Evaluation (66)
Property, plant and equipment (2,198)
Proceeds from the disposal of property, plant and
equipment
200
Other – Bond Refund 496
Proceeds from Exercise of Options 12
Proceeds from Borrowings 2,700
Repayment of borrowings (716)
Transaction Costs Related to Loans And Borrowings (95)
Cash Balance at End of Quarter $1,628
ASX Additional Information
The Company provides the following information pursuant to ASX Listing Rule requirements:
1. ASX Listing Rule 5.3.1: Exploration and Evaluation Expenditure spend during the quarter
was $66,000. Full details of exploration activity during the 31 March 2026 quarter are set
out in this report.
2. ASX Listing Rule 5.3.2: The Company confirms that mining production and development
activities occurred during the quarter at the Reward Underground Gold Mine. Ore
extraction and processing were undertaken on a campaign basis through the gravity-only
processing plant, with stoping operations active across multiple mining fronts as part of
the mine’s production ramp-up phase.
Expenditure on mining production and development activities during the quarter totalled
approximately $2.441 million, comprising:
a. $0.243 million of operating production expenditure (refer Appendix 5B item 1.2(c)),
which includes mining, haulage, processing and site overhead costs; and
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 16 of 27
b. $2.198 million of mine development and capital works, relating primarily to
underground development, maintenance of surface infrastructure, and continued
optimisation of the gravity-only gold plant.
Gold Production Summary - March 2026 Quarter (unaudited)
Metric
September 2025
Quarter
December 2025
Quarter
March 2026
Quarter
Development rehab (m) 11 146 161
Development advance (m) 33 149 115
Ore mined (t)1
2,163 5,241 6,038
Ore processed (t)2
to gravity 2,525 2,892 3,861
Waste to fill (t)3
1,116 3,897 3,267
Gold recovered (oz) 77 123 284
Gold sold (oz) 77 118 245
Average gold price realised
(A$/oz)
5,411 6,362 7,006
1
All production and processing data is subject to final metallurgical reconciliation and assay confirmation.
2
Ore processed to gravity represents the actual crushed ore sent to the gravity plant for processing after
the reject rock has been rejected by the ore sorter.
3
Waste to fill represents crushed rock rejected by the ore sorter to be returned to the mine for backfill.
4
All-in Sustaining Cost (AISC) metrics have not been disclosed for the quarter, as operations have not yet
reached steady-state production and the processing profile was materially impacted by the level of low-
grade stockpile and development material.
ASX Listing Rule 5.3.3: During the March 2026 quarter, the Company acquired
Exploration Licence 9868 (Dun Dun).
The Company did not dispose of any mining or exploration tenements during the quarter.
A full list of mining and exploration tenements held at 31 March 2026 is set out in the
Tenement Schedule below. Interests are held either directly by the Company, through its
subsidiaries, or pursuant to contractual arrangements.
All tenements remain in good standing.
Vertex Minerals Ltd Quarterly Activities Report - March 2026
Page 17 of 27
Mining tenements held at the end of the Quarter
Tenement Project Status Area Location
EL 5868 Hill End Current 16 Units NSW
EL 6996 Hargraves Renewal Pending 6 Units NSW
EL 9485 Hargraves Current 1 Unit NSW
EL 9564 Hill End Current 2 Units NSW
EL 8289 Hill End Current 1 Unit NSW
EL 9247 Hill End Current 2 Units NSW
EL 9413 Hill End Current 1 Unit NSW
GL 5846 Hill End Current 2.044 ha NSW
ML 49 Hill End Current 1.618 ha NSW
ML 50 Hill End Current 3.02 ha NSW
ML 315 Hill End Current 6.671 ha NSW
ML 316 Hill End Current 8.846 ha NSW
ML 317 Hill End Current 7 ha NSW
ML 913 Hill End Current 22 ha NSW
ML 914 Hill End Current 21.69 ha NSW
ML 915 Hill End Current 13.27 ha NSW
ML 1116 Hill End Current 15.71 ha NSW
ML 1541 Hill End Current 279.2 ha NSW
EPL 12008 Hill End Issued - -
E77/2651 Pride of Elvire Current 51km2 WA
E 63/2058 Taylors Rock Current 57km2 WA
EL 9434 Hill End Current 30 Units NSW
EL 9868 Hill End “Dun Dun” Current 22 Units NSW
Farm-in or Farm-out Agreements entered into during the Quarter
None
Beneficial Percentage Interests Held in Farm-in or Farm-out agreements at the end of the
Quarter
None
3. ASX Listing Rule 5.3.5: Payment to related parties of the Company and their associates
during the quarter was $175,694, in cash. Such payments related to directors’ fees and
consulting fees for both technical and management services.
End Notes