Quarterly Activities and Cash Flow Reports 31 December 2025
Released
Released
Announcement PDF
ABN 68 650 116 153
ASX ANNOUNCEMENT
30 January 2026
QUARTERLY ACTIVITIES REPORT
FOR THE PERIOD ENDED 31 DECEMBER 2025
HIGHLIGHTS FOR QUARTER
Operations - Underground Mining
• Continued ramp-up of underground gold production at the Reward Gold Mine, with
two stoping fronts active by quarter end across the Lady Belmore Reef and Mica vein
systems.
• Successful commissioning of tele-remote mining systems, enabling safe long hole
stoping and remote bogging beneath open stopes.
• First production firing of the high-grade 640 - MIST 1618N longhole stope, generating
approximately 80 tonnes of ore at ~16.6 g/t Au.
• Delivering a safe quarter of mining activities.
• Solid campaign on development of all three declines, with the mining team having
undertaken significant ongoing rehabilitation to make the ground safe and workable.
Processing
• The Reward gravity-only processing plant operated on underground ore throughout
the quarter, with optimisation activities supporting operation at or near design
capacity (nameplate throughput).
Corporate
• Execution of $4.5 million in loan facilities to support underground development,
production ramp-up and working capital requirements. With $1.2 million unutilised
and available for drawdown.
• Appointment of experienced mining executive Jim Simpson as a Director.
Tenements and Exploration
• Lodgement of an application for the “Dun Dun” exploration licence, expanding the
Company’s landholding along the Hill End-Hargraves gold corridor.
Overview
Vertex Minerals Limited (“Vertex” or “the Company”) is pleased to present its Quarterly
Activities Report for the quarter ended 31 December 2025.
The December quarter marked a pivotal phase in the Company’s transition from initial
underground production to a multi-front operating mine at the Reward Gold Mine. Building
on the development and commissioning activities undertaken in the September 2025
quarter, the Company focused during the December quarter on expanding stoping activity,
commissioning tele-remote mining capabilities, increasing ore grades, and optimising
processing plant performance.
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 2 of 25
By quarter end, two underground mining areas were in active stoping or advanced
development, with grades trending upward as mining progressed into planned production
zones. The Company also strengthened its balance sheet through the execution of additional
loan facilities to support the production ramp-up and working capital requirements.
Vertex Minerals Executive Chairman, Roger Jackson, commented:
“The December quarter represented a significant step forward for Vertex as the Reward Gold
Mine transitioned from initial underground production into an active ramp-up phase.
Following the recommencement of underground mining in the prior quarter, activities during
the period focused on expanding stoping activity and establishing more production fronts
across the Lady Belmore Reef and adjoining Mica vein systems.”
“During the quarter, the Company achieved several important operational milestones,
including the commissioning of tele-remote mining capability and the first firing of planned
longhole stopes. In particular, the initial firing of the 640 - MIST 1618N stope marked the
commencement of mechanised long hole stoping within the Lady Belmore Reef.”
“Plant performance and underground scheduling also progressed during the quarter as
additional mining areas were made operational. While the operation remains in the ramp-up
phase, the work completed during the period supports the continued advancement of
underground production and processing capacity as further stopes are developed. We have
been burdened by significant unplanned rehabilitation work in the declines which has clearly
slowed us up getting to productive stopes. However, we take safety seriously and wish to
make this mine productive and safe.”
“On the corporate front, we strengthened the Company’s balance sheet through the
execution of additional debt facilities to support the production ramp-up and working capital
requirements. These facilities provide the flexibility and headroom required as we transition
Reward toward steady-state production.”
“Looking ahead, our focus is on building momentum through 2026 by increasing stoping
rates, integrating additional ore sources and continuing to de-risk the operation. With
multiple mining fronts now established, tele-remote systems commissioned and a clear
development pathway in place, Vertex is well positioned to deliver sustained operational
progress.”
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 3 of 25
Operations
Reward Gold Mine (Hill End, NSW)
Background
The Hill End Gold Project is located in the Central Tablelands of New South Wales,
approximately 50 kilometres south of Mudgee, within the highly prospective Eastern Lachlan
Fold Belt. Vertex holds 155 km² of tenure across five exploration licences, one gold lease (GL
5846) and ten mining leases (ML 49, 50, 315, 316, 317, 913, 914, 915, 1116 and 1541).
The district has a rich gold mining history, with more than four million ounces historically
produced. Vertex’s ground position spans the Hill End corridor and includes several historic
high-grade mines. Mineralisation within the district is hosted within multiple laminated
quartz vein systems, with the Lady Belmore Reef and the adjacent Mica vein systems forming
the principal structures currently being developed.
The cornerstone of the Company’s development strategy is the Reward Gold Mine (Image 2),
a high-grade underground operation accessed via the existing 640 Level portal.
The Reward Gold Mine benefits from substantial existing infrastructure - a permitted
processing plant site, established portal, ventilation and services, permitted residue storage,
and road access. Together, these features provide a strong platform for Vertex’s transition
from explorer to producer.
Image 1: Map of the Hill End Project Area
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 4 of 25
Image 2: Reward Gold Mine (Northwest Looking)
Work completed during the quarter and results
During the December 2025 quarter, activities at Reward were directed toward transitioning
the operation from early production into a structured ramp-up phase. Key areas of focus
included:
• expansion of underground stoping across multiple levels;
• completion of rehabilitation works to unlock additional mining fronts;
• commissioning of tele-remote mining equipment;
• increasing the proportion of stoping ore relative to development ore; and
• optimisation of processing plant performance on hard-rock underground feed.
By 31 December 2025, five underground mining areas were either in active ore development
or stoping, reflecting the progressive advancement of planned development and production
activities across the Reward underground mine.
Development activities
During the December 2025 quarter, development activity at the Reward Gold Mine
continued to progress as operations moved toward steady-state production. In prior
quarters, development expenditure was comparatively higher, reflecting the establishment
of underground access, rehabilitation works and electrical infrastructure required to support
and access future mining areas.
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 5 of 25
As development works were completed during the quarter and additional stoping areas
became available, development activity reduced. Accordingly, a greater proportion of
underground mining activity during the quarter was directed toward ore extraction and
production, resulting in an increase in production-related costs, including labour costs.
This reflects the Company’s ongoing transition toward steady-state operations, with total
mining effort focused on production as the Reward Gold Mine increases the number of
mining fronts.
Underground Mining Operations
Mica Vein System
1438 North Long hole Stope
The 1438 North long hole stope, which targets the Mica vein system, was an active
production development area during the December 2025 quarter (Image 3). This stope
represents one of the first mechanised long hole stoping panels being brought into
production at the Reward Gold Mine and forms part of the Company’s initial production
ramp-up sequence.
Image 3: Longitudinal section of the Reward underground workings showing the Lady Belmore Reef adjoining
(including the 1438 Stope)
During the December 2025 quarter, the Company progressed the implementation of tele-
remote mining capability at the Reward Gold Mine. Aramine 350D loaders fitted with tele-
remote capability, together with the associated tele-remote hut system, were delivered to
the Hill End site on 24 October 2025. Following delivery, the required software updates
enabling communication between the loaders and the tele-remote hut were completed, with
the tele-remote system becoming available for operational use in early December 2025
(Image 4).
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 6 of 25
Image 4 - Tele-hut being taken underground
Prior to tele-remote availability, the 1438 North long hole stope had been drilled and fired,
with broken ore available for extraction in previous quarters. While limited free-bog material
was removed, most of the broken ore required tele-remote capability to enable safe loading
from beneath open stopes. As part of underground scheduling during the quarter, the 1438
North stope was brought forward in the production sequence from its original March 2026
timing. In parallel, the T1D was refitted for production long hole stoping and subsequently
fired, allowing stoping activities to continue while tele-remote implementation was finalised.
Following commissioning, the tele-remote system was incorporated into underground
operations, enabling remote bogging of broken ore from beneath open stopes (Image 5). By
late December 2025, initial extraction of broken ore from the 1438 North stope had largely
been completed, with continued extraction to proceed in accordance with the planned
sequence. The 1438 North stope was utilised during the quarter as part of the commissioning
and validation of tele-remote long hole stoping practices at the Reward Gold Mine,
supporting the ongoing production ramp-up.
Image 5: Tele-remote bogging in 1438 North stop
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 7 of 25
Decline 1, 2 and 3 - Mica 1 and Mica 2 Veins
Mining development and rehabilitation activities continued in Declines 1, 2 and 3 during the
December 2025 quarter following the completion of a geotechnical assessment covering
these areas. Together, the declines form the primary access network to historically
productive areas associated with the Mica vein system.
In Decline 3, development progressed along the Mica 1 and Mica 2 vein systems during the
December 2025 quarter, with backs progressively increased to approximately four metres,
accommodating a planned flat-back stoping. Rehabilitation and ground-support works were
undertaken at the same time to restore access through historical workings and prepare the
area for subsequent stoping activities. At quarter end, approximately 22 metres of
rehabilitation remained to be completed in Decline 3 before the commencement of flat-back
stoping can occur.
Rehabilitation works also continued in Declines 1 and 2, which extend below the adit level
and have historically acted as sumps. During the quarter, rehabilitation across Declines 1 and
2 focused on improving ground conditions, installing additional ground support and restoring
safe access through previously flooded sections.
Lady Belmore Reef Development
The Lady Belmore Reef is the principal ore source at the Reward Gold Mine and underpins
Vertex’s current underground mining development activities. Located west of the modern
decline, the Lady Belmore Reef comprises a well-defined, laminated quartz vein system that
has been extensively mined historically within Hill End.
During the December 2025 quarter, underground mining activities within the Lady Belmore
Reef continued to focus on the advancement of planned stoping areas as part of the
production ramp-up.
640 – MIST 1618N Long hole Stope
The 640 - MIST 1618N long hole stope, located within the Lady Belmore Reef, was advanced
during the December 2025 quarter as part of the Company’s planned transition to
mechanised long hole stoping within the high-grade system.
The first production firing at the 640 - MIST 1618N stope occurred on 19 December 2025,
generating approximately 80 tonnes of broken ore from a total planned stope inventory of
approximately 277 tonnes - at a reported grade of approximately 16.6 g/t Au. This firing
marked the commencement of planned stoping activities within the stope panel.
Additionally, tele-remote mining systems were installed beneath the open stope to enable
the safe extraction of broken ore during the quarter.
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 8 of 25
Other Mineralised Structures
Star of Peace Vein – 1600 Level Development
Development along the Star of Peace vein at the 1600 level continued during the December
2025 quarter, with activities focused on access and geological evaluation to support potential
future stoping assessment.
During the December 2025 quarter, development along the Star of Peace structure
intersected mineralised material consistent with historical workings. Such developments
have provided a way forward for both geological mapping and sampling concerning the
structure.
Processing and Gold Production
The Reward gravity-only processing plant operated on underground ore throughout the
December 2025 quarter as the Company continued its transition from development and
stockpiled material to run-of-mine underground feed.
During the quarter, the Company progressed processing plant optimisation, including a
planned shutdown to implement targeted modifications aimed at improving plant
performance. These works included adjustments to screen sizing to optimise feed
presentation to the TOMRA ore sorter, together with modifications to improve compatibility
with the VSI crusher. The changes were implemented to support more consistent processing
of harder underground ore and to reduce recirculating loads within the circuit.
Gold sales during the quarter totalled approximately $751,000, reflecting deliveries of gravity
gold concentrate produced from underground ore. At 31 December 2025, additional gravity
gold concentrate had been produced and was held on hand pending delivery, consistent with
the ongoing ramp-up of underground ore production and processing throughput.
Hargraves Gold Project (Hill End, NSW)
Background
The Hargraves Project is located approximately 35 kilometres north of Hill End in the Central
Tablelands of New South Wales, within the highly prospective Eastern Lachlan Fold Belt. The
project comprises two granted exploration licences (EL 6996 and EL 9485) covering the
historical Hargraves Goldfield. The area has a rich mining history, with more than 1.4 million
ounces of gold historically produced from reef and alluvial workings.
Hargraves hosts a JORC-compliant Mineral Resource of 2.3 million tonnes at 2.4 g/t Au for
178,000 ounces (refer page 17 of this report). Its proximity to Hill End positions Hargraves as
a logical potential satellite ore source, supporting the Company’s strategy of developing Hill
End as a centralised processing hub.
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 9 of 25
Work completed during the quarter
No work was completed during the quarter for the Hargraves Gold Project.
Taylor Rock Project
Background
The Taylor Rock Project (E63/2058) lies on the southeastern margin of the Lake Johnston
Greenstone Belt in Western Australia, approximately 190 km southwest of Kalgoorlie. The
geological setting is highly prospective, with historic drilling identifying pegmatite swarms
that may host lithium-bearing spodumene, as well as nickel sulphide potential from past
exploration campaigns by Norilsk Nickel.
Image 6: Map of the Taylor Rock Project
Work completed during the quarter
No work was completed during the quarter for the Taylor Rock Project.
Pride of Elvire Project
Background
The Pride of Elvire Project (E77/2651, ~51 km²) is located in the Mt. Elvire greenstone belt in
Western Australia, approximately 210 km north of Southern Cross. The project area is
historically known for small-scale gold mining, and previous explorers have undertaken
stream, soil and rock chip sampling, as well as RAB and RC drilling.
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 10 of 25
Image 7: Map of the Pride of Elvire Project
Work completed during the quarter
No work was completed during the quarter for the Pride of Elvire Project.
Tenement Acquisition and Tenure Update
Dun Dun Exploration Licence Application (ELA 6978)
During the December 2025 quarter, Vertex lodged an application for a new exploration
licence, ELA 6978 (Dun Dun).
The Dun Dun tenement is located between the Company’s Reward and Hargraves project
areas. If granted, the Dun Dun tenement will form a strategic addition to Vertex’s landholding.
The application was lodged to consolidate the Company’s tenure position along a continuous
strike length of the Hill End gold system, improving regional continuity between its existing
project areas.
The Dun Dun area hosts historical gold workings, including the Dun Dun and Longmore-
Reward vein systems, which are geologically analogous to the laminated quartz vein
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 11 of 25
mineralisation observed at Reward. Historical mining records indicate that these structures
were worked to relatively shallow depths, consistent with other historically productive areas
within the Hill End Goldfield.
Subject to grant, the Company intends to incorporate the tenement into its broader Hill End
exploration strategy, including geological mapping, surface sampling and prioritisation for
future exploration activities.
Image 8: Map of ELA 6978 “Dun Dun”
Corporate
Board and Management
On 19 December 2025, Mr Jim Simpson was appointed as a Director of Vertex Minerals
Limited. Mr Simpson brings extensive experience in underground mining operations, mine
development and operational leadership, which is expected to support the Company as it
advances through the production ramp-up phase.
On the same date, Mr Declan Franzmann retired from the Board. Mr Franzmann was a
Director of the Company since its early development stages and made a significant
contribution to the progression of the Reward Gold Mine from development into production.
Annual General Meeting Results
The Company held its Annual General Meeting of shareholders on 28 November 2025. All
resolutions put to shareholders were passed by poll. The results of the meeting were released
to the ASX following the conclusion of the AGM.
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 12 of 25
At the AGM, shareholders approved the appointment of BDO Audit Pty Ltd as auditor of the
Company, pursuant to section 327B(1)(b) of the Corporations Act 2001 (Cth).
Funding and Financial Position
During the December 2025 quarter, the Company executed additional loan facilities totalling
$4.5 million to support the ongoing ramp-up of underground operations at the Reward Gold
Mine.
The facilities provide additional liquidity and working capital headroom to fund underground
development activities, processing plant optimisation and general operating requirements
during the production ramp-up phase. The funding was secured to ensure the Company
maintains sufficient flexibility as production volumes increase and gold sales progressively
scale. Further details concerning the terms of the loan facilities can be found within the
Company’s announcement to the ASX dated 24 December 2025.
Allotment of Equity Securities
During the December 2025 quarter, the Company issued a number of equity securities in
connection with previously announced capital raisings. On 16 October 2025, the Company
issued:
• 2,506,313 listed options (VTXOA) to participants in the June 2025 Share Purchase Plan
(SPP); and
• 25,591,048 ordinary fully paid shares and 37,090,224 listed options (VTXOA) in
connection with the placement and conversion of loan securities associated with the
July 2025 funding package and under the terms of the relevant capital raising and
financing arrangements previously announced to the market.
Conversion of Options
On 27 October 2025, a total of 321,896 VTXO options were exercised, resulting in the issue of
321,896 ordinary fully paid shares in the Company and the receipt of additional funds.
Investor Relations
During the December 2025 quarter, the Company’s Chairman, Roger Jackson, presented at
the Australian Gold Conference. The presentation provided an overview of Vertex Minerals’
operations and strategy, with a particular focus on the Reward Gold Mine and the Company’s
transition into underground production.
The Australian Gold Conference is a well-established industry forum attended by institutional
and retail investors, analysts and industry participants.
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 13 of 25
Financial
As at 31 December 2025, the Company had A$1,497,999 in cash (unaudited).
Vertex’s expenditure during the Quarter was as follows:
Item A$ (‘000s)
Cash Balance at beginning of Quarter 3,277
Receipts from customers 754
Production Costs (2,007)
Staff Costs (1,034)
Administration and Corporate Costs (577)
Exploration and Evaluation (119)
Property, plant and equipment (2,120)
Proceeds from the disposal of property, plant and
equipment
1,048
Issue of equity securities and convertible debt
securities
3,359
Costs of equity raising and borrowings (253)
Repayment of borrowings (802)
Transaction Costs Related to Loans And Borrowings (28)
Cash Balance at End of Quarter $1,498
ASX Additional Information
The Company provides the following information pursuant to ASX Listing Rule requirements:
1. ASX Listing Rule 5.3.1: Exploration and Evaluation Expenditure spend during the quarter
was $118,096. Full details of exploration activity during the 31 December 2025 quarter
are set out in this report.
2. ASX Listing Rule 5.3.2: The Company confirms that mining production and development
activities occurred during the quarter at the Reward Underground Gold Mine. Ore
extraction and processing were undertaken on a campaign basis through the gravity-only
processing plant, with stoping operations active across multiple mining fronts as part of
the mine’s production ramp-up phase.
Expenditure on mining production and development activities during the quarter totalled
approximately $4.13 million, comprising:
a. $2.01 million of operating production expenditure (refer Appendix 5B item 1.2(c)),
which includes mining, haulage, processing and site overhead costs; and
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 14 of 25
b. $2.12 million of mine development and capital works, relating primarily to
underground development, maintenance of surface infrastructure, and continued
optimisation of the gravity-only gold plant.
Gold Production Summary - December 2025 Quarter (unaudited)
Metric December 2025 Quarter
Ore mined (t)1
5,241
Ore processed (t)2
6,789
Gold recovered (oz) 123
Gold sold (oz) 118
Average gold price realised (A$/oz) 6,362
1
All production and processing data is subject to final metallurgical reconciliation and assay confirmation.
2
Ore feed for the quarter was predominantly sourced from low-grade stockpiles, with the balance comprising
material from underground development headings and stoping. Development ore was further diluted with
other development and waste material, which was processed due to available plant throughput and the
application of ore sorting technology. The composition of the ore mined was as follows:
Development Ore 4,125
Stoping Ore 1,116
Total 5,241
3
All-in Sustaining Cost (AISC) metrics have not been disclosed for the quarter, as operations have not yet
reached steady-state production and the processing profile was materially impacted by the level of low-
grade stockpile and development material.
ASX Listing Rule 5.3.3: During the quarter, the Company did not acquire or dispose of any
mining or exploration tenements.
During the quarter, the Company lodged an application for a new exploration licence, ELA
6978 (Dun Dun), located between the Company’s existing Hill End (Reward) and Hargraves
project areas in New South Wales. The application remains pending as at the end of the
quarter.
A full list of mining and exploration tenements held at 31 December 2025 is included in
the Tenement Schedule below. Interests may be held directly by the Company, through a
subsidiary, or under contractual arrangements.
All tenements remain in good standing.
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 15 of 25
ining tenements held at the end of the Quarter
Tenement Project Status Area Location
EL 5868 Hill End Current 16 Units NSW
EL 6996 Hargraves Renewal Pending 6 Units NSW
EL 9485 Hargraves Current 1 Unit NSW
EL 9564 Hill End Current 2 Units NSW
EL 8289 Hill End Current 1 Unit NSW
EL 9247 Hill End Current 2 Units NSW
EL 9413 Hill End Current 1 Unit NSW
GL 5846 Hill End Current 2.044 ha NSW
ML 49 Hill End Current 1.618 ha NSW
ML 50 Hill End Current 3.02 ha NSW
ML 315 Hill End Current 6.671 ha NSW
ML 316 Hill End Current 8.846 ha NSW
ML 317 Hill End Current 7 ha NSW
ML 913 Hill End Current 22 ha NSW
ML 914 Hill End Current 21.69 ha NSW
ML 915 Hill End Current 13.27 ha NSW
ML 1116 Hill End Current 15.71 ha NSW
ML 1541 Hill End Current 279.2 ha NSW
EPL 12008 Hill End Issued - -
E77/2651 Pride of Elvire Current 51km2 WA
E 63/2058 Taylors Rock Current 57km2 WA
EL 9434 Hill End Current 30 Units NSW
ELA 6978 Hill End Application Pending 22 Units NSW
Farm-in or Farm-out Agreements entered into during the Quarter
None
Beneficial Percentage Interests Held in Farm-in or Farm-out agreements at the end of the
Quarter
None
3. ASX Listing Rule 5.3.5: Payment to related parties of the Company and their associates
during the quarter was $247,563, in cash. Such payments related to directors’ fees and
consulting fees for both technical and management services.
End Notes
The information contained in this announcement related to the Company’s past exploration
results is extracted from, or was set out in, the following ASX announcements which are
referred to in this Quarterly Activities Report:
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 16 of 25
Date of announcement Name of announcement
17/10/2025 VTX Secures Adjoining Exploration Licence
Application
27/10/2025 Ore Production Update Reward Gold Mine
10/11/2025 Ore Production Update Reward Gold Mine
11/11/2025 Resignation and Proposed Appointment of
Auditor
17/11/2025 Ore Production Update Reward Gold Mine
28/11/2025 Results of Annual General Meeting
19/12/2025 Retirement and Appointment of Directors
23/12/2025 Ore Production Update Reward Gold Mine
24/12/2025 Reward Project Secured $4.5m Loan Facilities
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 17 of 25
ABOUT VERTEX
Hill End NSW:
• 14km of Continuous gold lode
• Gold recovers to gravity at +90%
• Most of the line of lode only mined to the water table
• The Hill End Gold project consists of 10 mining leases & 4 Exploration licenses located
in the core of the Hill End Trough on the eastern Lachlan Fold Belt.
• The area was first recognised as a gold centre in 1851 with a number of mining
operations established over the following 50 years
• Gravity Plant on site
• Fully permitted Gravity processing licence
• Reward Underground High-Grade Gold Mine – mine ready
Reward Gold Mine: 2.0g/t reporting cutoff grade
Hargraves: 0.8 g/t reporting cutoff grade (ASX Announcement 29 May 2020).
Red Hill: 0.5 g/t per block, ordinary kriging grade interpolation, classified mineral Resources Limited to 160mRL
below surface. (ASX Announcement November 2015
Hargraves NSW:
• Hargraves Gold project is located approximately 25km south of the town of Mudgee.
• The goldfield is 4 x 10 km with numerous mineralised structures with little modern
exploration.
• An updated mineral resource in accordance with JORC 2012 Code was completed by
SRK Consulting (Australasia) Pty Ltd (SRK).
• The Board will prioritise the development of this project by updating PFS, permitting
and further drilling to increase resources.
Vertex Minerals Ltd Quarterly Activities Report – December 2025
Page 18 of 25
To learn more, please visit: www.vertexminerals.com
Stay up to date with the latest news by connecting with VTX on LinkedIn and Twitter.
Follow Vertex Minerals on LinkedIn
Competent Persons Statement
The information in this report that relates to the Reward Gold Mineral Resource estimate is
based on information compiled by Mr. Troy Lowien, who is a full-time employee of
Groundwork Plus. Mr. Lowien is a member of the Australasian Institute of Mining and
Metallurgy (FAusIMM), and has sufficient experience which is relevant to the style of
mineralisation and type of deposits under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined in the 2012 Edition of the
“Australasian Code for Reporting of Exploration results, Mineral Resources and Ore Reserves”.
Mr. Lowien consents to the inclusion of the data contained in relevant resource reports used
for this announcement as well as the matters, form and context in which the relevant data
appears.
The information in this report that relates to Exploration Results, Exploration Targets and the
Hargraves and Red Hill Resource Estimates is based on information compiled by Mr. Roger
Jackson. Mr. Jackson is a Director and Shareholder of the