Reward Gold Mine and Company Update
Released
Released
Announcement PDF
Vertex Progress Update at the High-Grade Reward
Gold Mine.
ASX Announcement 27th of November 2024
HIGHLIGHTS
•
All major components are now installed and fitted at the Reward Gold Mine Gravity Plant.
•
Electrical fit out is well underway.
•
Piping and water reticulation is ongoing.
•
Tails lines are being laid to the dry sand stack location.
•
Plant power up is planned for mid-December.
•
General Manager and other key personnel have commenced employment.
•
Ore Sorter structure is under construction and will be installed in January
•
The plant will be commissioned on stockpiles located at the plant prior to the Ore Sorter installation.
•
Road infrastructure upgraded.
•
Portal entry and ore handling area refurbished and expanded.
•
Vertex on track for January commissioning of the plant.
The Reward Gold Mine is well placed for a simple start –up:
•
The new processing plant is being constructed adjacent to the underground mine portal (640 Level) and over
the existing footprint of the existing plant.
•
The 640 Level extends into the resource and no stripping required with the revised mine plan.
•
Second egress in place with existing ladder way from 640 Level to surface.
•
Some underground fleet and utility services are already owned by Vertex, with new fleet arriving.
•
The New plant will utilise the existing services and infrastructure:
ü Gold Room
ü
ü
ü
ü
Water systems
Power generation
Offices
Change Rooms
ü
ü
ü
ü
ü
ü
ü
Workshop
Storeroom
Crib Room
Jaw Crusher
Access Roads
Security System
Tails site
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
Vertex Minerals Limited (ASX:VTX) (“Vertex” or the “Company”) is pleased to announce a further
update on the Reward Gold mine start up.
Operational
Gravity Plant
Mobilisation of the Gravity Plant from Ballart to site commenced earlier this month (as announced 13
November 2024), with all major components now onsite, installed and fitted at the Gravity Plant. Fitout
of ancillary services (including electrical and water) is well underway, with completion and initial
powering-up scheduled for mid-December 2024.
All Civil Works for this stage, including the upgrading and refurbishment of Road Infrastructure, portal
entry and the ore handling area are also complete.
Ore Sorter and Forward Plan
Compelling results from Ore Sorting testwork (including a 337% increase in grade and 79% mass
reduction) as announced on 25th July 2024, resulted in a decision to incorporate pre-concentration
into the flow sheet and design for the Hill End project (as announced 11 September 2024). Construction
of the Ore Sorter structure has commenced, with installation expected in January 2025. Installation of
the Ore Sorter is not expected to delay plant commissioning, with initial processing of existing stockpiles
located at the plant location to commence prior to installation and commissioning of the Ore Sorter.
Corporate and Financial
On 7 November 2024, Shareholders voted to approve the second tranche of the Company’s 2-tranche
share placement announced in mid-August 2024. All funds for the second tranche have been received
and allotment is expected shortly.
The Company’s Annual General Meeting (AGM) is scheduled for 29 November 2024 and resolutions
include approval for the conversion of loan funds received under the capital-raising announced in
October 2024. Various option issue approvals were granted in the 7 November Meeting and are being
sought at the AGM and a prospectus for the issue of those options is being prepared.
On 27 May 2024 the Company announced that it had signed a terms sheet with Ocean Partners for a
US$10M Prepayment Facility, subject to conditions precedent. Following on from the revised mine
design and Gravity plant flow sheet, because of the decision to utilise an ore sorter, the capital
expenditure required to develop the mine was significantly lowered. A facility of this size is no longer
expected to be required by the Company and the parties have agreed that the proposed arrangement
will not be completed, with no penalty to the Company. The Company is in negotiations with several
parties in relation to a significantly smaller debt or prepayment facility.
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
Commenting on the progress, Vertex Executive Chairman Roger Jackson said: “We are very excited by
the progress that has been made with the Gravity Gold plant installation at our mine ready Gold project.
The installation is well ahead of the time we had scheduled, which has helped recover the time lost due
to weather with the civil construction. We are hopeful we can now power the plant up for testing in just
a few weeks. We then can commission the plant with the gold ore stockpiles we have sitting at the plant.
I would commend Gekko and our Hill End team for their efforts with this installation.”
Figure 1 Gekko Gravity Plant tower looking back on Gold room
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
Figure 2 View of the installed plant from Gravity concentrator side
Figure 3 View over the Primary and secondary crusher
W. www.Vertexminerals.com
E. info@vertexminerals.com.au
This announcement has been approved by the Board of Vertex Minerals Limited.
Further Information:
Roger Jackson, Executive Chairman
roger@vertexminerals.com.au
Tully Richards, Technical Director
tully@vertexminerals.com.au
Follow Vertex Minerals on LinkedIn
About Vertex Minerals Limited
Vertex Minerals Limited (ASX: VTX) is an Australian-based gold mining and exploration company developing
its advanced Hill End gold projects located in the highly prospective Eastern Lachlan Fold Belt of Central
West NSW. Other Company assets include the Pride of Elvire gold project and Taylor Rock
gold/nickel/lithium project both located in the Eastern Goldfields of WA. The focus of Vertex Minerals is to
advance the commercial production of gold from its NSW projects embracing an ethical and environmentally
sustainable approach:
• Gravity Recoverable Gold
• Low Capex and Low Operating cost
• Minimal grind 200 to 500 micron
• Benign tails – potential commercial sand
• Benign waste
• Low water usage
• Re usable water
• No chemicals – no cyanide
• 23 fine gold
• Minimum tails to productivity
Global Mineral Resource estimate for the Hill End & Hargraves Gold Project
Hill End Project Mineral Resource Estimate
Deposit
Classification
Tonnes
Grade
(kt)
Au (g/t)
Reward Gold Mine
Indicated
141
15.5
Inferred
278
17.3
Sub Total
419
16.7
Contained
Au (koz)
71
155
225
Hargraves Project
Indicated
Inferred
1,109
1,210
2,319
2.7
2.1
2.4
97
80
178
Indicated
Inferred
413
1,063
1,476
1.4
1.8
1.7
19
61
80
Indicated
Inferred
1,663
2,551
4,214
3.5
3.6
3.6
187
296
483
Sub Total
Red Hill Project
Sub Total
Project Total
Grand Total
Hargraves Gold Project (NSW)
•
Hargraves Gold project is located approximately 25 km south of the town of Mudgee.
•
The goldfield is 4 x 10 km with numerous mineralised structures with little modern exploration.
•
An updated mineral resource in accordance with JORC 2012 Code was completed by SRK Consulting
(Australasia) Pty Ltd (SRK) – a total of 2.3Mt at 2.38g/t Au for 177koz Au.
Hill End Gold Project (NSW)
•
Consists of 10 mining leases and three Exploration Licenses located in the core of the Hill End Trough
on the eastern Lachlan Fold Belt.
•
Gravity Gold Plant
•
PFS completed for the Reward Gold Mine
•
24 km of continuous gold lode with gold recovery rate to gravity at +90%.
Pride of Elvire Gold Project (WA)
•
Tenements surround the Mt. Elvire homestead approximately 21 0km north of Southern Cross in
Western Australia
•
The project has seen historical drilling with encouraging gold results achieved.
Taylor Rock Project (WA)
•
Located 80 km WSW of Norseman in the Southern Goldfields region of Western Australia.
•
The project has both Gold and Nickel potential, interesting historical intercepts have recorded
encouraging mineralisation.
Competent Persons Statement
The information in this report that relates to Exploration Results and Exploration Targets is based on
information compiled by Mr. Roger Jackson, a Director and Shareholder of the Company, who is a 25+ year
Fellow of the Australasian Institute of Mining and Metallurgy (FAusIMM), Fellow of the Australian Institute of
Geoscientists (FAIG) and a Member of Australian Institute of Company Directors. Mr. Jackson has sufficient
experience which is relevant to the style of mineralisation and type of deposits under consideration and to the
activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the
“Australasian Code for Reporting of Exploration results, Mineral Resources and Ore Reserves”. Mr. Jackson
consents to the inclusion of the data contained in relevant resource reports used for this announcement as
well as the matters, form and context in which the relevant data appear.
Forward Looking Statements and Important Notice
This report contains forecasts, projections and forward-looking information. Although the Company believes
that its expectations, estimates and forecast outcomes are based on reasonable assumptions it can give no
assurance that these will be achieved. Expectations and estimates and projections and information provided
by the Company are not a guarantee of future performance and involve unknown risks and uncertainties,
many of which are out of Vertex Minerals’ control.
Actual results and developments will almost certainly differ materially from those expressed or implied. Vertex
Minerals has not audited or investigated the accuracy or completeness of the information, statements and
opinions contained in this announcement. To the maximum extent permitted by applicable laws, Vertex
Minerals makes no representation and can give no assurance, guarantee or warranty, express or implied, as
to, and takes no responsibility and assumes no liability for the authenticity, validity, accuracy, suitability or
completeness of, or any errors in or omission from, any information, statement or opinion contained in this
report and without prejudice, to the generality of the foregoing, the achievement or accuracy of any forecasts,
projections or other forward looking information contained or referred to in this report. Investors should make
and rely upon their own enquiries before deciding to acquire or deal in the Company’s securities.
JORC Compliance Statements
Where statements in this announcement refer to exploration results which previously been reported, the
Company confirms that it is not aware of any new information or data that materially affects the information
included in the original announcements, and in the case of estimates of Mineral Resources, that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcements
continue to apply and have not materially changed. The Company confirms that the form and context in which
the Competent Persons’ findings are presented have not materially modified from the original market
announcements.
1 For further details of the current resource at Reward, refer ASX Announcement dated 26 June 2023
2 For further details of the resource at Hargraves and Red Hill, refer to the IGR in the Company’s listing
prospectus dated 21 October 2021 and released on ASX on 12 January 2022.