Quarterly Activities and Cash Flow Reports 30 September 2025
Released
Released
Announcement PDF
ABN 68 650 116 153
ASX ANNOUNCEMENT
31 October 2025
QUARTERLY ACTIVITIES REPORT
FOR THE PERIOD ENDED 30 SEPTEMBER 2025
HIGHLIGHTS FOR QUARTER
• Commencement of underground ore production at the Reward Gold Mine, marking
transition to high-grade gold production.
• Processed first freshly-blasted ore from underground stoping blocks and development
drives, totalling 625 tonnes through the gravity-only gold plant during the quarter.
• Establishment of multiple underground mining fronts over approximately 400 metres of
strike, providing operational flexibility.
• Stoping of the 1670 airleg stope commenced; drilling of the 1438 long hole stope also
commenced late September with production scheduled in October.
• Development of the 1720 cut-and-fill stope advancing, and preparation of a new
development drive on the Amalgamated Vein to open additional production areas.
• Installation and energisation of the 11 kV underground power network, commissioning of
the 110 kW primary ventilation fan, and completion of mine-wide radio communications.
• Delivery of a new Aramine 350D tele-remote loader to enhance production capability and
safety.
• Ongoing optimisation of the gravity-only processing circuit with continued gold recovery
improvement; no chemicals or cyanide used in processing.
• Continuous expansion of underground development expected to increase gold output
through Q4 2025.
Overview
Vertex Minerals Limited (“Vertex” or “the Company”) is pleased to present its Quarterly
Activities Report for the quarter ended 30 September 2025.
Following more than twelve months of mine re-entry works, plant commissioning, and
infrastructure upgrades, the quarter delivered the Company’s first gold-bearing ore
production, confirming the readiness of the Reward operation to transition into steady-state
output. Ore production began in August 2025 and by quarter-end, Vertex had mined and
processed its first high-grade underground ore, achieving strong recoveries through the
newly commissioned gravity-only plant. Multiple mining fronts were established, major
infrastructure was completed, and the Company took substantial steps toward sustained
operations.
Overall, the quarter positions Vertex as a new Australian gold producer with operational
momentum, a clear pathway for production growth, and an experienced management team
focused on responsible, profitable mining.
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 2 of 25
Vertex Minerals Executive Chairman, Roger Jackson, commented:
“The September quarter marked a pivotal milestone for Vertex, with the commencement of
underground ore production at the Reward Gold Mine in Hill End. Following more than a year
of planning, rehabilitation and infrastructure works, our team successfully re-entered the
Reward workings and delivered the first high-grade ore from the Lady Belmore Reef in August.
This achievement represents the formal transition of Reward from development into
production, and I could not be prouder of the team for executing this safely and efficiently.”
“During the quarter, we were also able to establish multiple production fronts across the Lady
Belmore Reef and adjoining Mica veins, confirming both grade continuity and operational
readiness. These outcomes provide a solid foundation for the ramp-up phase now under
way.”
“On the corporate front, we advanced our previously announced A$11 million capital-raising
program, with the completion of the Tranche 2 placement after the Company’s general
meeting. This funding strengthens our balance sheet and ensures Vertex is well-resourced to
continue mine development and expand production capacity in the months ahead.”
“Looking forward, the December quarter will see continued long hole stoping in the now
developed mining fronts and the integration of additional ore sources to support steady-state
production. With a clear development pathway, strong technical performance and a focused
team on site, Vertex is positioned to generate sustained operational momentum through to
2026.”
Operations
Reward Gold Mine (Hill End, NSW)
Background
The Hill End Gold Project is located in the Central Tablelands of New South Wales,
approximately 50 kilometres south of Mudgee, within the highly prospective Eastern Lachlan
Fold Belt. Vertex holds 155 km² of tenure across five exploration licences, one gold lease (GL
5846) and ten mining leases (ML 49, 50, 315, 316, 317, 913, 914, 915, 1116 and 1541).
The district has a rich gold mining history, with more than four million ounces historically
produced. Vertex’s ground position spans the Hill End corridor and includes several historic
high-grade mines. The cornerstone of the Company’s development strategy is the Reward
Gold Mine, a high-grade underground deposit accessed via the existing 640 Level portal.
The Reward Gold Mine benefits from substantial existing infrastructure - a permitted
processing plant site, established portal, ventilation and services, permitted residue storage,
and road access. Together, these features provide a strong platform for Vertex’s transition
from explorer to producer.
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 3 of 25
Image 1: Map of the Hill End Project Area
Work completed during the quarter and results
Transition to Underground Production
During the September 2025 quarter, Vertex achieved a major operational milestone with the
commencement of first underground ore production at the Reward Gold Mine in Hill End,
New South Wales. This milestone marked the re-opening of one of Australia’s most
historically prolific gold systems - the Lady Belmore Reef, a structure renowned for producing
some of the highest grades ever recorded within the Hill End goldfield.
Following twelve months of rehabilitation and infrastructure works, the Reward
underground mine was safely re-opened for full operational access in early August 2025,
enabling the commencement of stoping and ore haulage. All mechanical, electrical and
safety systems were commissioned, including the new 11 kV power reticulation network
(Image 2), upgraded pumping infrastructure, and a fully integrated mine-wide
communications system. These installations enabled the safe commencement of production
stoping within the central section of the Lady Belmore Reef and the adjoining Mica 1 and
Mica 2 veins (Image 3).
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 4 of 25
Image 2: High voltage (11 kV) transformer installed next to power station at the Reward Gold plant
Image 3: Longitudinal section of the Reward underground workings showing the Lady Belmore Reef adjoining
Mica 1 and Mica 2 vein systems, showing active production areas (1670, 1438, and 1720 stopes).
The first stope was fired in mid-August 2025, and ore was hauled to surface through the
refurbished 1670 Level Decline (Images 4 and 5). This event formally marked the transition
of Reward from commissioning into production. Subsequent firing and bogging operations
during mid-to-late September 2025, particularly within the 1670 airleg and 1438 long hole
stopes, confirmed the predicted vein geometry, grade continuity and ground conditions
established in pre-production modelling. These early mining results validated the geological
model and demonstrated the operational readiness of the underground mine.
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 5 of 25
Image 4: Lady Belmore Reef being charged up and house down the ore, post blasting
Image 5: Truck being loaded with ore and hauled to processing plant from the Lady Belmore Reef vein
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 6 of 25
Ore Production and Geological Setting
By late September 2025, Vertex had completed the initial phase of underground production
at the Reward Gold Mine, establishing a consistent and reliable ore-to-plant supply chain.
During August 2025, the Company’s first underground campaign produced approximately
500 tonnes of ore from a combination of development headings and early stoping areas. This
material graded between 5 and 6 grams per tonne (g/t) gold and achieved recoveries of
about 90+ percent through the Reward gravity-only plant. These results confirmed the
mine’s readiness for continuous operations and validated the efficiency of the chemical-free
processing circuit.
In September 2025, underground activity expanded with the commencement of the 1670
Airleg Shrink Stope within the Lady Belmore Reef system, which delivered an additional 125
tonnes of ore over a five-day production period. This marked the transition from
commissioning to sustained, multi-stope operations, with ore sourced from both the Lady
Belmore Reef and the adjoining Mica 1 and Mica 2 veins. The combination of these ore
sources provided flexibility in mill feed and supported consistent gold grades as underground
production ramped up toward quarter-end.
The first parcels of underground material were processed through the Reward gravity-only
plant during late August and September 2025. The plant performed to expectation, operating
reliably and in line with design parameters, and achieved metallurgical recoveries of 90+
percent. These results provided early validation of the chemical-free gravity circuit,
confirming both the efficiency of the process design and its environmental performance.
Throughout the quarter, the plant ran steadily with no material mechanical interruptions,
demonstrating readiness for sustained, continuous operation as underground ore supply
increases in the coming months following quarter-end.
Lady Belmore Reef Development
The Lady Belmore Reef is the principal ore source at Reward, providing the structural and
geological foundation for Vertex’s underground production strategy. Situated immediately
west of the modern decline, the reef has long been recognised as one of Hill End’s most
prolific gold-bearing structures, historically producing exceptionally high-grade ore from
narrow quartz veins. Its re-emergence as the central production zone marks a significant
milestone in the revival of this famous field.
During the September 2025 quarter, Vertex established several active mining fronts within
the Reward Underground Mine as part of its transition to continuous production. Multiple
mining methods are being applied to optimise ore recovery and head grade across the Lady
Belmore Reef and Mica vein systems, including airleg shrink stoping, long hole open stoping,
and jumbo cut-and-fill techniques. Image 2 contains the cross sections of the Lady Belmore
Reef, with the active production areas (1670, 1438 and 1720 stopes).
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 7 of 25
1670 Level Production Stope
The first of these fronts, the 1670 Airleg Shrink Stope, entered production in August 2025
and was in full operation by late September 2025. Stoping progressed steadily, with
approximately 125 tonnes of ore mined and processed over a five-day period leading up to
the end of the quarter. Ore from this stope was processed through the Reward gravity plant,
with concentrates further refined for gold recovery (Image 6).
The 1670 stope targets low-tonnage, high-grade zones within the Lady Belmore Reef and has
performed in line with expectations, confirming the continuity of mineralisation and ground
stability observed in development.
Image 6: High grade veins in the back of the 1670 Shrink Stope
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 8 of 25
1438 Long hole Stope
Drilling commenced on the 1438 Long hole Stope on 23 September 2025, marking the second
production front established within the mine. This stope has been designed to target the
Mica 1 and Mica 2 veins (Image 7), with planned production of approximately 660 tonnes at
a conservative grade of 6 g/t Au.
Blasting commenced in early October 2025, providing additional high-grade ore sources to
support continuous feed to the plant.
Image 7: Oblique view of 1438 Long hole Stope
1720 Cut and Fill Stopes
Preparations also advanced during the quarter for the 1720 Cut-and-Fill Stopes located in
Decline 3, where ground stripping, backing, and installation of new ground support were
undertaken to facilitate jumbo access ahead of first ore production occurring in October
2025.
In parallel, the Company commenced development along the Amalgamated Vein, a structure
outside the defined Resource envelope. This heading provides both exploration exposure
and access to potential new ore blocks. Geological mapping and sampling along this drive
confirmed the presence of quartz-sulphide veining similar in character to the productive
Mica veins. This area will form part of the next phase of stope-design work.
By late October 2025, daily ore haulage and continuous processing had been achieved,
confirming the mechanical readiness of the operation and the quality of the Reward ore
system. Mining is expected to advance southwards along the Lady Belmore Reef and deeper
into the historical high-grade zones during the December 2025 quarter, laying the foundation
for increased output and steady-state production through to the 2026 financial year.
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 9 of 25
Underground Infrastructure
To support underground production, Vertex completed installation of primary and secondary
ventilation systems, undertook ground-support rehabilitation using galvanised mesh and
resin bolts, and constructed new escapeways and refuge chambers. Dewatering systems
were commissioned on 5 August 2025, and the mine remains dry and fully ventilated.
Major underground infrastructure was otherwise completed during the September 2025
quarter, transforming Reward into a fully functioning production mine. The new 11 kV
underground power system was commissioned, providing electricity across all levels (Image
1). The 110 kW primary ventilation fan was installed and operational by 21 August 2025,
delivering the airflow necessary for mechanised stoping (Image 8). Secondary ventilation
circuits were also completed to service development headings.
Image 8: Installation of 110kW ventilation fan
Additionally, water and air reticulation lines were extended throughout the decline system
during the quarter, and the 1555 Decline was dewatered to full depth, re-establishing access
to historical workings. The mine now has a fully integrated services network supporting both
production and development.
A new mine-wide communications network, incorporating digital radio and Wi-Fi coverage,
was installed and commissioned during the quarter. This upgrade provides continuous
communication between underground crews and surface control, improving both
operational coordination and emergency response capability. Complementing these safety
enhancements, an Aramine 350D tele-remote loader arrived on site late in the period.
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 10 of 25
The unit enables remote bogging of ore from active stopes, allowing production to continue
efficiently while minimising personnel exposure in higher-risk zones.
Processing Plant Operations
The Reward gravity-only processing plant operated continuously throughout the September
2025 quarter. The plant uses a combination of crushing, screening, centrifugal concentration
and tabling to produce clean gold concentrates without the use of cyanide or other reagents.
Several optimisation initiatives were implemented during the quarter to enhance reliability
and throughput. A new DSM screen was installed to improve classification efficiency, Gemini
table gearboxes were refurbished, and a process-water pump system was fitted to
strengthen circulation and water recovery.
Safety and Workforce
During the September 2025 quarter, Vertex maintained a stable site workforce at the Reward
Gold Mine under its owner-operator model, comprising both Vertex employees and
specialist underground and processing contractors. This model continued to provide
operational flexibility and direct control over production and safety performance.
Final commissioning of the INX Safety Management System was completed during the
quarter, providing full functionality for real-time incident reporting, hazard tracking, and
training compliance. The system has strengthened onsite governance and improved visibility
across all operations.
No Lost Time Injuries or reportable safety incidents occurred during the period.
Environmental and Community Performance
During the September 2025 quarter, Vertex maintained full compliance with all
environmental and regulatory conditions at the Reward Gold Mine. The gravity-only
processing circuit continued to operate as a closed-loop system with high water-recycling
efficiency and no use of cyanide or other chemical reagents. No reportable environmental
incidents occurred during the period.
Environmental monitoring of water, dust and noise levels continued in line with existing site
management plans. Water consumption remained low due to the efficiency of the on-site
recycling system.
Vertex continued to engage constructively with the local Hill End community and regional
suppliers throughout the quarter. The Company’s commitment to low-impact, chemical-free
gold production remains a key element of its social-licence approach and has been positively
received by local stakeholders.
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 11 of 25
Hargraves Gold Project (Hill End, NSW)
Background
The Hargraves Project is located approximately 35 kilometres north of Hill End in the Central
Tablelands of New South Wales, within the highly prospective Eastern Lachlan Fold Belt. The
project comprises two granted exploration licences (EL 6996 and EL 9485) covering the
historical Hargraves Goldfield. The area has a rich mining history, with more than 1.4 million
ounces of gold historically produced from reef and alluvial workings.
Hargraves hosts a JORC-compliant Mineral Resource of 2.3 million tonnes at 2.4 g/t Au for
178,000 ounces. Its proximity to Hill End positions Hargraves as a logical potential satellite
ore source, supporting the Company’s strategy of developing Hill End as a centralised
processing hub.
Work completed during the quarter
No work was completed during the quarter for the Hargraves Gold Project.
Taylor Rock Project
Background
The Taylor Rock Project (E63/2058) lies on the southeastern margin of the Lake Johnston
Greenstone Belt in Western Australia, approximately 190 km southwest of Kalgoorlie. The
geological setting is highly prospective, with historic drilling identifying pegmatite swarms
that may host lithium-bearing spodumene, as well as nickel sulphide potential from past
exploration campaigns by Norilsk Nickel.
Image 9: Map of the Taylor Rock Project
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 12 of 25
Work completed during the quarter
No work was completed during the quarter for the Taylor Rock Project.
Pride of Elvire Project
Background
The Pride of Elvire Project (E77/2651, ~51 km²) is located in the Mt. Elvire greenstone belt in
Western Australia, approximately 210 km north of Southern Cross. The project area is
historically known for small-scale gold mining, and previous explorers have undertaken
stream, soil and rock chip sampling, as well as RAB and RC drilling.
Image 10: Map of the Pride of Elvire Project
Work completed during the quarter
No work was completed during the quarter for the Pride of Elvire Project.
.
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 13 of 25
Corporate
Board and Management
On 2 July 2025, Vertex announced the resignation of Non-Executive Director Mr Sean
Richardson. The Board expressed its appreciation for Mr Richardson’s contribution to the
Company and wished him well in his future endeavours.
General Meeting Results
Vertex held a General Meeting on 21 July 2025 at which all resolutions were passed by poll.
Shareholders ratified prior share placements and approved the issue of convertible securities
and options to investors and lenders.
Funding and Financial Position
During the quarter, Vertex advanced its A$11 million capital-raising program, comprising
placements and a subsequent Share Purchase Plan. Proceeds from the placement tranches
received in August and September 2025 strengthened the Company’s funding position for
ongoing mine development, plant optimisation and production ramp-up. At quarter-end,
Vertex held a solid cash balance and maintained a conservative debt profile, providing
sufficient liquidity to support underground expansion and operational growth into the
December 2025 quarter.
Financial
As at 30 September 2025, the Company had A$3,276,899 in cash (unaudited).
Vertex’s expenditure during the Quarter was as follows:
Item A$ (‘000s)
Cash Balance at beginning of Quarter 1,725
Receipts from customers 418
Production Costs (1,232)
Interest and costs of finance (2)
Administration and Corporate Costs (1,197)
Exploration and Evaluation (102)
Property, plant and equipment (4,589)
Issue of equity securities and convertible debt
securities, net of costs
9,134
Costs of equity raising and borrowings (541)
Repayment of borrowings (337)
Cash Balance at End of Quarter $3,277
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 14 of 25
ASX Additional Information
The Company provides the following information pursuant to ASX Listing Rule requirements:
1. ASX Listing Rule 5.3.1: Exploration and Evaluation Expenditure spend during the quarter
was $101,647. Full details of exploration activity during the 30 September 2025 quarter
are set out in this report.
2. ASX Listing Rule 5.3.2: The Company confirms that mining production and development
activities occurred during the quarter at the Reward Underground Gold Mine. Ore
extraction and processing were undertaken on a campaign basis through the gravity-only
processing plant, with stoping operations active across multiple mining fronts as part of
the mine’s production ramp-up phase.
Expenditure on mining production and development activities during the quarter totalled
approximately $5.8 million, comprising:
a. $1,231,984 of operating production expenditure (refer Appendix 5B item 1.2(c)),
which includes mining, haulage, processing and site overhead costs; and
b. $4,588,865 of mine development and capital works (refer Appendix 5B item 2.3),
relating primarily to underground development, maintenance of surface
infrastructure, and continued optimisation of the gravity-only gold plant.
Gold Production Summary – September 2025 Quarter (unaudited)
Metric September 2025 Quarter
Ore mined (t)2
2,163
Ore processed (t)2
5,873
Gold recovered (oz) 76.82
Gold sold (oz) 76.82
Cash cost (A$/oz) 39,049
Average gold price realised (A$/oz) 5,411
1
All production and processing data is subject to final metallurgical reconciliation and assay confirmation.
2
Ore feed for the quarter was predominantly sourced from development headings and low-grade
stockpiles/waste.
3. ASX Listing Rule 5.3.3: No mining or exploration tenements were acquired or disposed of
during the quarter.
A full list of mining and exploration tenements held at 30 September 2025 is included in
the Tenement Schedule below. Interests may be held directly by the Company, through a
subsidiary, or under contractual arrangements.
All tenements remain in good standing.
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 15 of 25
Mining tenements held at the end of the Quarter
Tenement Project Status Area Location
EL 5868 Hill End Renewal Pending 16 Units NSW
EL 6996 Hargraves Renewal Pending 6 Units NSW
EL 8289 Hill End Current 1 Unit NSW
EL 9247 Hill End Current 2 Units NSW
EL 9413 Hill End Current 1 Unit NSW
GL 5846 Hill End Current 2.044 ha NSW
ML 49 Hill End Current 1.618 ha NSW
ML 50 Hill End Current 3.02 ha NSW
ML 315 Hill End Current 6.671 ha NSW
ML 316 Hill End Current 8.846 ha NSW
ML 317 Hill End Current 7 ha NSW
ML 913 Hill End Renewal Pending 22 ha NSW
ML 914 Hill End Renewal Pending 21.69 ha NSW
ML 915 Hill End Renewal Pending 13.27 ha NSW
ML 1116 Hill End Current 15.71 ha NSW
ML 1541 Hill End Current 279.2 ha NSW
ELA 6466 Hill End South Application Pending 30 Units NSW
EPL 12008 Hill End Issued - -
E77/2651 Pride of Elvire Current 51km2 WA
E 63/2058 Taylors Rock Current 57km2 WA
ELA 6466 Hill End South Application Pending 30 Units
EPL 12008 Hill End Issued - -
Farm-in or Farm-out Agreements entered into during the Quarter
N/A
Beneficial Percentage Interests Held in Farm-in or Farm-out agreements at the end of the
Quarter
N/A
4. ASX Listing Rule 5.3.5: Payment to related parties of the Company and their associates
during the quarter was $440,603, in cash. Such payments related to directors’ fees and
consulting fees for both technical and management services.
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 16 of 25
End Notes
The information contained in this announcement related to the Company’s past exploration
results is extracted from, or was set out in, the following ASX announcements which are
referred to in this Quarterly Activities Report:
Date of announcement Name of announcement
3 July 2025 Resignation of Director
9 July 2025 Reward Gold Mine Project Update
11 August 2025 Reward Gold Mine Project Update -
Underground Production Commences at
Reward Gold Mine
25 August 2025 Ore Production Update - Reward Underground
Gold Mine
24 September 2025 Ore Production Update - Reward Underground
Gold Mine
ABOUT VERTEX
Hill End NSW:
• 14km of Continuous gold lode
• Gold recovers to gravity at +90%
• Most of the line of lode only mined to the water table
• The Hill End Gold project consists of 10 mining leases & 4 Exploration licenses located
in the core of the Hill End Trough on the eastern Lachlan Fold Belt.
• The area was first recognised as a gold centre in 1851 with a number of mining
operations established over the following 50 years
• Gravity Plant on site
• Fully permitted Gravity processing licence
• Reward Underground High-Grade Gold Mine – mine ready
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 17 of 25
Reward Gold Mine: 2.0g/t reporting cutoff grade
Hargraves: 0.8 g/t reporting cutoff grade (ASX: HEG Announcement 29 May 2020).
Red Hill: 0.5 g/t per block, ordinary kriging grade interpolation, classified mineral Resources Limited to 160mRL
below surface. (ASX: HEG Announcement 30 November 2015)
Hargraves NSW:
• Hargraves Gold project is located approximately 25km south of the town of Mudgee.
• The goldfield is 4 x 10 km with numerous mineralised structures with little modern
exploration.
• An updated mineral resource in accordance with JORC 2012 Code was completed by
SRK Consulting (Australasia) Pty Ltd (SRK).
• The Board will prioritise the development of this project by updating PFS, permitting
and further drilling to increase resources.
Vertex Minerals Ltd Quarterly Activities Report – September 2025
Page 18 of 25
To learn more, please visit: www.vertexminerals.com
Stay up to date with the latest news by connecting with VTX on LinkedIn and Twitter.
Follow Vertex Minerals on LinkedIn
Competent Persons Statement
The information in this report that relates to the Reward Mineral Resource estimate is based
on information compiled by Mr. Troy Lowien, who is a full-time employee of Groundwork Plus.
Mr. Lowien is a member of the Australasian Institute of Mining and Metallurgy (FAusIMM),
and has sufficient experience which is relevant to the style of mineralisation and type of
deposits under consideration and to the activity which he is undertaking to qualify as a
Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of
Exploration results, Mineral Resources and Ore Reserves”. Mr. Lowien consents to the
inclusion of the data contained in relevant resource reports used for this announcement as
well as the matters, form and context in which the relevant data appears.
The information in this report that relates to Exploration Results, Exploration Targets and the
Hargraves and Red Hill Resource Estimates is based on information compiled by Mr. Roger
Jackson. Mr. Jackson is a Director and Shareholder of the Company, who is a Fellow of the
Australasian Institute of Mining and Metallurgy (FAusIMM), Fellow of the Australasian
Institute of Geoscientists and a Member of Australian Institute of Company Directors. Mr.
Jackson has sufficient experience which is relevant to the style of mineralisation and type of
deposits under consideration and to the activity which he is undertaking to qualify as a
Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of
Exploration results, Mineral Resources and Ore Reserves”. Mr. Jackson consents to the
inclusion of the data contained in relevant resource reports used for this announcement as
well as the matters, form and context in which the relevant data appears.
JORC Compliance Statements
This website contains references to Mineral Resource estimates, which have been extracted
from previous ASX announcements as set out above made by Peak Resources Ltd (ASX:PUA),
the parent company of VTX prior to the Company’s separate listing in 2022. For full details of
Exploration Results in this release that have been previously announced, refer to those
announcements.
The Company confirms that it is not aware of any new information or data that materially
affects the information included in the said announcements, and in the case of estimates of
Mineral Resources, that all material assumptions and technical parameters underpinning the
estimates in the relevant market announcements continue to apply and have not materially
changed. The Company confirms that the form and context in which the Competent Persons’
findings are presented have not materially modified from the original market announcements.
Forward Looking Statements and Important Notice