First gold bar poured
Operational milestones
✓ Vertex has poured its maiden gold bar weighing close to 1kg of gold. Previously,
gold was sold as a concentrate (~30% gold). Two gold bars have been poured this
month.
✓ With both the DA Modification and the varied EPL now in place, the Reward Gold
Mine is conducting underground mining 12 hours a day, 7 days a week, with
underground blasting permitted at any hour within the licensed limits. This has
made a considerable improvement in productivity.
✓ The next step is to move to 24 hours a day for mining operations and 12 hours a
day for processing.
✓ A total of 44oz of gold was sold in September 2026, with a further 22oz of gold on
hand at the refinery and another 60oz to be sold as low-grade gold concentrate. An
offtake agreement is being negotiated with third parties.
✓ September 2026 production was achieved while the mine was still operating under
restricted hours and blasting times, and with limited equipment availability. The
full benefit of continuous operations and the additional equipment will be
reflected from October 2026 onwards.
✓ The trial long hole open stope at Decline 3 (620 M1 STP 1695N) has been
completed. Whilst the grades were not as high as expected, the stoping method
and the ability to stope narrow veins have proven a great success.
✓ Development of the smaller drive profiles has started using the new Muki rail
boom arrangements fitted to the jumbos, which are now reducing dilution by more
than 20%.
✓ The second Bird underground truck has been commissioned and is now in
operation (Figure 8).
✓ The Resemin Muki LHBP-2R long hole drill is expected to be commissioned on site
in early November 2026.
*Statements regarding expected productivity, cost and production outcomes are forward looking and are based on the
Company’s current mine plan and operating assumptions. They are not production targets and do not constitute a Mineral
Resource or Ore Reserve estimate. Refer to the Forward Looking Statements notice at the end of this announcement.
ASX:VTX
2
Vertex Minerals Limited (ASX: VTX) (“Vertex” or “the Company”) is pleased to provide an
operational update on the Reward Gold Mine.
Blasting times
Blasting is now being conducted at any time, 7 days per week, within the licensed limits. With
this flexibility of timing, hours are saved every shift.
Trial long hole stope
The trial long hole open stope at Decline 3 (620 M1 STP 1695N), targeting the high-grade Mica 1
lens, has been a technical success, with stoping complete and panels 4 and 5 extracted. The
stope is being filled ready for the next lift. See Figures 1 and 5.
This success supports the Company’s move to mechanised long hole stoping. The Company’s
dedicated Resemin Muki long hole production drill rig is en route to Australia.
Figure 1 – Trial long hole open stope at Decline 3 (620 M1 STP 1695N), showing the reduced stope width (left) and the open
stope (right)
Development and new drive profiles
The first of the new, smaller drive profiles on the individual Mica veins is being mined using the
Muki boom arrangements. The smaller profiles, as expected, are reducing dilution and improving
the grade to the processing plant (Figure 2). With the smaller headings, the reduction in ground
support, drill holes, explosives and bogging time, the cycle time has reduced. Focus now is
maximizing the development metres.
ASX:VTX
3
Figure 2 – New smaller drive profile on the Mica veins: face marked up for drilling (left) and completed narrow ore drive (right)
Metallurgy
A key breakthrough has been achieved with the introduction of a spiral wheel, which upgrades
the gold concentrate from the Wilfley and Gemini gold tables. The concentrate purity from these
tables has historically been ~30%. In order to smelt gold, a concentrate of >50% is required;
hence, past gold concentrates have been sold to a third-party refinery (Figure 3).
Figure 3 – Spiral wheel upgrading the gold table concentrate (left) and the first gold bar poured at the Reward Gold Mine (right)
Equipment
The Resemin Muki LHBP-2R long hole drill was completed at the Resemin factory on 30
September 2026 and is currently in transit to Australia. It is expected to arrive in Australia in mid-
November (Figures 9 and 10).
Long hole open stoping is a key component of Vertex’s planned mining operations at the Reward
Gold Mine. The introduction of the Muki LHBP-2R is therefore an important step towards
establishing the drilling capability required to prepare and extract stope ore. Its ability to drill
ASX:VTX
4
accurate long holes will support the planned transition towards increased stope production and
more consistent underground ore supply.
Planning update
The mine plan has been updated to reflect continuous operations. Near-term focus areas
include:
✓ the 677 PX STP 1472N airleg stope has been completely scraped out and mining
has commenced on the next panel to the south (Figure 6);
✓ the 683 North Ore Drive and the North Paxtons stoping block development have
been completed and are ready for stoping (Figure 7);
✓ the 618 Level Mica 1 North ore drive and the Star of Peace South ore drives off the
Decline 2 bypass and Decline 3, and the take-off from Decline 1 on M2, are the
current headings; and
✓ once the Decline 3 long hole stope has been filled, the next lift will be supported
ready for the Muki long hole rig.
September 2026 production
✓ Gold produced: 39oz; gold sold: 44oz; gold on hand: 82oz
✓ Development: 68m advance and 13m rehabilitation
October 2026 forecast
✓ Development on ore at Declines 1, 2 and 3 (Figure 4), with five ore headings
✓ Development: +100m advance on day shift
✓ Preparation to move to night shift and increase to +180m/month for future
months
✓ Production: ~100oz
November 2026 forecast
✓ Development on ore at 618L and 628L, Decline 3 (Figure 5), with five ore headings
✓ Development: +120m advance on day and night shift
✓ Increase to +180m/month for future months
✓ Production: ~150oz
December 2026 forecast
✓ Development on ore at 618L and 628L, Decline 3 (Figure 5), with five ore headings
✓ Development: +180m advance on day and night shift
✓ Production: ~500oz
ASX:VTX
5
Figure 4 – Reward Gold Mine long section showing scheduled development by month, October 2026 to January 2027. The red
box marks the Decline 3 area shown in Figure 5
Figure 5 – Decline 3 and 657 Level, showing the completed trial stope (620 M1 STP 1695N), the 620 M1 stopes to the north and
the 633 Star of Peace access drive. Colours as per Figure 4
ASX:VTX
6
Figure 6 – 677 Level southern airleg stoping area, showing the completed 677 PX STP 1474N stope and the next stopes to the
south. Colours as per Figure 4
Figure 7 – North 683 airleg stoping area, showing the completed 683 North Ore Drive and the planned stopes. Colours as per
Figure 4
ASX:VTX
7
Figure 8 – Bird Systems 10-tonne underground truck ready to commence underground operations at the Reward Gold Mine
Figure 9 – Vertex Minerals’ Muki LHBP-2R long hole drill at the Resemin factory in September 2026, fitted with an HC95LM rock
drill
ASX:VTX
8
Figure 10 – Vertex Minerals’ Muki LHBP-2R long hole drill at the Resemin factory in September 2026, showing the boom
equipped with a magazine
Vertex Executive Director Operations, Jim Simpson, commented:
“There have been many impediments to ramping up the mine as originally planned. Whilst there
have been significant delays, we are still in a position to ramp up operations from October 2026
onwards.”
This announcement has been approved for release to the ASX by the Directors of Vertex
Minerals Limited.
ASX:VTX
9
FURTHER INFORMATION
Telephone +61 2 7229 4849
or by email at info@vertexminerals.com.au
Bruce McInnes, Executive Chairman
Roger Jackson, Executive Director
Jim Simpson, Executive Director Operations
Tully Richards, Director
COMPETENT PERSON’S STATEMENT
The information in this announcement that relates to mining and production results is based on information
compiled by Mr Roger Jackson, a Director and Shareholder of the Company, who is a 25+ year Fellow of the
Australasian Institute of Mining and Metallurgy (FAusIMM), Fellow of the Australian Institute of Geoscientists (FAIG)
and a Member of the Australian Institute of Company Directors. Mr Jackson is the Executive Director and a full-time
employee of Vertex Minerals Limited (“Company”), and a shareholder of the Company. Mr Jackson has sufficient
experience which is relevant to the style of mineralisation and type of deposit under consideration, and to the
activity which he is undertaking, to qualify as a Competent Person as defined in the 2012 Edition of the
“Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Jackson consents
to the inclusion of the matters, form and context in which the relevant data appear in this announcement.
FORWARD LOOKING STATEMENTS AND IMPORTANT NOTICE
This announcement contains forecasts, projections and forward-looking information, including in relation to the
Company’s mining methods, rostering, equipment delivery, development rates, operating costs and production
plans. Although the Company believes that its expectations, estimates and forecast outcomes are based on
reasonable assumptions, it can give no assurance that these will be achieved. Expectations, estimates, projections
and information provided by the Company are not a guarantee of future performance and involve unknown risks
and uncertainties, many of which are out of Vertex Minerals’ control. The statements in this announcement
regarding expected productivity, cost and ore supply outcomes are not production targets and are not based on an
Ore Reserve estimate.
Actual results and developments will almost certainly differ materially from those expressed or implied. Vertex
Minerals has not audited or investigated the accuracy or completeness of the information, statements and opinions
contained in this announcement. To the maximum extent permitted by applicable laws, Vertex Minerals makes no
representation and can give no assurance, guarantee or warranty, express or implied, as to, and takes no
responsibility and assumes no liability for, the authenticity, validity, accuracy, suitability or completeness of, or any
errors in or omission from, any information, statement or opinion contained in this announcement, including as to
the achievement or accuracy of any forecasts, projections or other forward-looking information contained or
referred to in this announcement. Investors should make and rely upon their own enquiries before deciding to
acquire or deal in the Company’s securities.
Share your feedback
Discover