Operational Update - Varied EPL Issued
Released
Released
Announcement PDF
ASX:VTX
1
ASX ANNOUNCEMENT 18 SEPTEMBER 2026
OPERATIONALUPDATE,
VARIED EPL ISSUED – 24/7 UNDERGROUND OPERATIONS NOW
FULLY APPROVED AT REWARD GOLD MINE
Working hours lift from 9 to 22 per day, with no additional equipment required
Operational Milestones
✓ Vertex has been issued a varied Environment Protection License (EPL 12008) by the
NSW Environment Protection Authority (EPA), aligning the license with the DA
Modification approved by Bathurst Regional Council (ASX:VTX announcement 20
August 2026 “Development Application Modification Approved”).
✓ With both the DA Modification and the varied EPL now in place, the Reward Gold
Mine is authorised to conduct underground mining 24 hours a day, 7 days a week,
with underground blasting permitted at any hour within the licensed limits.
✓ This is a step change for the Company: available working hours underground move
from approximately 9 hours per day to approximately 22 hours per day, fully utilising
the equipment already on site.
✓ Processing will be conducted on a full 12 hours a day basis rather than the past 10
hours per day.
✓ 49oz of gold was sold in August 2026, with a further 81oz of gold on hand and
available for sale.
✓ The trial long hole open stope at Decline 3 (620 M1 STP 1695N) continues to deliver
technical learnings and successes, with Panel 1, 2 and 3 complete and Panel 4 in
progress.
✓ New, smaller, drive profiles are about to be mined using the new Muki rail boom
arrangements fitted to the Jumbos, which are expected to reduce dilution by more
than 20% for the same cut length.
✓ The second Bird underground truck has arrived in Orange, NSW, where it is being
fitted with the modifications required for MDG 15 compliance, and is expected to
be on site within a couple of weeks.
✓ Resemin Muki LHBP-2R Long Hole drill is to be shipped from factory, by 30
September 2026.
*Statements regarding expected productivity, cost and production outcomes are forward looking and are based on the Company’s
current mine plan and operating assumptions. They are not production targets and do not constitute a Mineral Resource or Ore
Reserve estimate. Refer to the Forward Looking Statements notice at the end of this announcement.
ASX:VTX
2
Vertex Minerals Limited (ASX: VTX) (“Vertex” or “the Company”) is pleased to advise that the NSW
EPA has issued a varied Environment Protection License (EPL 12008) for the Reward Gold Mine at
Hill End, NSW. The varied EPL follows, and aligns with, the DA Modification approved by Bathurst
Regional Council and announced to the market on 20 August 2026. With both approvals now in
place, the Company has the regulatory authority to operate the Reward underground mine on a
continuous 24-hour, 7-day basis.
What the varied EPL authorises
The varied EPL sets out the approved hours for each activity at the premises:
✓ Mining (underground operations, including transportation, rehabilitation,
environmental management and emergency operations): 24 hours, 7 days per week.
✓ Processing (the Amalgamated Processing Plant and associated infrastructure):
6:00am to 6:00pm, 7 days per week.
✓ Non-audible maintenance of site infrastructure, plant and services: 24 hours, 7 days
per week, within the licensed noise limits.
✓ Construction and audible maintenance: 6:00am to 6:00pm, 7 days per week.
Blasting is permitted at any time, 7 days per week, subject to the licensed limits. All blasting is
carried out underground. Between 9:00am and 6:00pm, ground vibration at any dwelling or
sensitive receiver must not exceed 10.0 mm/sec (peak particle velocity) at any time and must not
exceed 5.0 mm/sec for more than 5% of blasts over any 12-month period. Between 6:00pm and
9:00am, ground vibration must not exceed 2.0 mm/sec (peak particle velocity). Airblast
overpressure at noise-sensitive locations must not exceed 115dB (Lin Peak) for more than 5% of
blasts in a reporting period and must not exceed 120dB (Lin Peak) at any time.
Why this is a step change for Vertex
Until now, every mining cycle at Reward has been governed by a single firing window from 9:00am
to 3:00pm, six days a week, with no firing on Sundays or public holidays. This caused major
disruption within the shift losing up to two hours per day when firing. If a heading was not charged
and cleared in time before 3pm that day, the cycle rolled forward 24 hours.
The varied EPL removes that constraint. The Company expects the following benefits*:
✓ More development metres: development is the primary driver of production ore,
and every metre of ore drive opens further production fronts
✓ More ore feed to the processing plant: Development headings and long hole stope
ore can be bogged through the night.
✓ Re-entry at shift change: ventilation clearance can be scheduled across shift
changes and crib breaks, rather than consuming the core of a working shift.
✓ Higher equipment utilization: Equipment now available for 24hrs/day
✓ Lower unit operating costs: a largely fixed cost base (fleet, ventilation, dewatering,
the Gekko gravity plant and the TOMRA ore sorter) is spread across materially more
tonnes.
ASX:VTX
3
✓ A smoother feed to the plant: consistent ore supply to the ROM pad allows the ore
sorter and gravity circuit to be scheduled with greater confidence.
✓ Better return on capital already spent: no additional mining equipment is required,
and with recent investment in the Muki rails, the Muki long hole rig and the second
Bird truck, the full complement of equipment required to operate the mine 24/7 is
complete.
Trial long hole stope
The trial long hole open stope at Decline 3 (620 M1 STP 1695N), targeting the high-grade Mica 1
lens, has provided a range of learnings and technical successes since the first panel was fired at
the end of July 2026 (ASX:VTX announcement 3 August 2026 “Reward Gold Mine Pivotal Point -
Stope Mining Commences”). Panels 1,2,3 have been completed with firings progressing in Panel 4.
Key achievements include stoping widths of 1.0 – 1.4m and full depth of firing (8-9m stope height).
Drilling accuracy is reasonably good considering it was conducted using a jumbo and extension
steels. Some dilution has incurred at the brow due to the drives being four metres wide. The new
drive profiles (2.5m) will reduce this overbreak significantly. See Figure 3.
This success supports the Company’s move to mechanised long hole stoping. The Company’s
dedicated Resemin Muki long hole production drill rig is confirmed for completion of construction
in late-September 2026, ahead of shipping to Australia.
Development and new drive profiles
Muki rails and drifters have been fitted to the front-line Atlas Copco H104 Jumbo. The first of the
new, smaller drive profiles on the individual Mica veins are about to be mined using the Muki
boom arrangements. The smaller profiles are expected to reduce dilution by more than 20% for
an equivalent cut length, improving the grade of ore delivered to the ROM pad*. Development
rehabilitation was completed during August 2026.
Equipment
The second Bird underground truck has arrived in Orange, NSW, where it is being fitted with the
modifications required for compliance with MDG 15 (the NSW guideline for mobile and
transportable equipment used in mines). The truck is expected to be on site within the next couple
of weeks and will increase haulage capacity coupled with continuous operations.
Planning update
The mine plan has been updated to reflect continuous operations. Near-term focus areas include:
✓ the 677 PX STP 1472N airleg stope, where Lifts 1 to 5 have been completed and now
being scraped out with a further airleg panel planned (Figure 2);
✓ the 683 North ore drive and the North Paxtons airleg stoping block (Figure 1);
✓ the 618 Level Mica 1 ore drive and 600 Level Bypass off Decline 2, the Star of Peace
Ore Drive; and the take-off from Decline 1 on the Mica 1 vein.
ASX:VTX
4
August 2026 production
✓ Ore processed: 1262t at 1.62g/t Au, with 64% recovery
✓ Gold produced: 94oz; gold sold: 49z; gold on hand: 81oz
✓ Development: 38m advance and 9m rehabilitation
From previous trials, gravity processing recoveries improve with higher feed grades. The current ore feed is still diluted
material.
Workforce and community
All blasting authorised under the DA Modification and the varied EPL is carried out underground.
Figure 1 Reward Gold Mine Main Development Areas
Figure 2 677 Level Main Airleg Stoping Area
ASX:VTX
5
Figure 3 Decline 3 Long Hole Stope
Vertex Executive Director Operations, Jim Simpson, commented:
“The varied EPL completes the approval process for the DA Modification (2000) which up to now
has heavily constrained the development of the mine. Restricted hours and blasting times have
been the biggest impediment in bringing the mine into full production.
With continuous operations, improving the development rates, developing more long hole stopes
and reducing dilution from the new ore drive profiles, it places Vertex in a far superior position to
achieve its long term production goals.”
This announcement has been approved for release to the ASX by Directors of Vertex Minerals
Limited.
FURTHER INFORMATION
Telephone +61 2 7229 4849
or by email at info@vertexminerals.com.au
Bruce McInnes, Executive Chairman
Roger Jackson, Executive Director
Jim Simpson, Executive Director Operations
Tully Richards, Director
ASX:VTX
6
COMPETENT PERSON’S STATEMENT
The information in this announcement that relates to mining and production results is based on information compiled
by Mr. Roger Jackson, a Director and Shareholder of the Company, who is a 25+ year Fellow of the Australasian
Institute of Mining and Metallurgy (FAusIMM), Fellow of the Australian Institute of Geoscientists (FAIG) and a Member
of the Australian Institute of Company Directors. Mr Jackson is the Executive Director and a full-time employee of
Vertex Minerals Limited (“Company”), and a shareholder of the Company. Mr. Jackson has sufficient experience which
is relevant to the style of mineralisation and type of deposit under consideration, and to the activity which he is
undertaking, to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting
of Exploration Results, Mineral Resources and Ore Reserves”. Mr. Jackson consents to the inclusion of the matters,
form and context in which the relevant data appear in this announcement.
FORWARD LOOKING STATEMENTS AND IMPORTANT NOTICE
This announcement contains forecasts, projections and forward-looking information, including in relation to the
Company’s mining methods, rostering, equipment delivery, development rates, operating costs and production plans.
Although the Company believes that its expectations, estimates and forecast outcomes are based on reasonable
assumptions, it can give no assurance that these will be achieved. Expectations, estimates, projections and
information provided by the Company are not a guarantee of future performance and involve unknown risks and
uncertainties, many of which are out of Vertex Minerals’ control. The statements in this announcement regarding
expected productivity, cost and ore supply outcomes are not production targets and are not based on an Ore Reserve
estimate.
Actual results and developments will almost certainly differ materially from those expressed or implied. Vertex
Minerals has not audited or investigated the accuracy or completeness of the information, statements and opinions
contained in this announcement. To the maximum extent permitted by applicable laws, Vertex Minerals makes no
representation and can give no assurance, guarantee or warranty, express or implied, as to, and takes no responsibility
and assumes no liability for, the authenticity, validity, accuracy, suitability or completeness of, or any errors in or
omission from, any information, statement or opinion contained in this announcement, including as to the
achievement or accuracy of any forecasts, projections or other forward-looking information contained or referred to
in this announcement. Investors should make and rely upon their own enquiries before deciding to acquire or deal in
the Company’s securities.